- 10:13 Task #7066 (Internal Testing): [CR00063] - Item1. To display all transactions (all status) detail...
- Hi Akmal,
Kindly proceed on internal testing.
March 09, 2017
- 18:21 Task #7066: [CR00063] - Item1. To display all transactions (all status) details on Bulk Payment, ...
- URL for testing
IBAM: https://172.16.50.27/ibam.sit.kada2/common/Login.do
BIB: https://172.16.50.27/bib.sit.kada2... - 15:20 Task #7100 (Prepare Test Script): [BRS_CR064-1] : Auto Sweeping Setting
- Hi Erni,
Kindly review the BRS and prepare for test script. Thank you
March 08, 2017
March 07, 2017
- 16:24 Task #7066 (Finished Development): [CR00063] - Item1. To display all transactions (all status) de...
- Hi Kak Haida,
The task is completed. Please refer bib branch "KADA_Enhancement2" for this enhancement.
March 06, 2017
- 17:25 Task #7067 (Development / Work In Progress): [CR00063] - Item5. Enable Audit Trail of User activi...
- 16:44 Task #7096 (Prepare Test Script): [BRS_CR063-Item1] :To display all transactions (all status) det...
- Hi Akmal,
Kindly proceed to review the BRS and prepare test script. Thank you - 16:24 Change #7044 (Development / Work In Progress): CR-00055 version 1.4 - ISS Intergration (Batch File)
- Hi Chee PingH, email from Ila date 1/3/2017
As discussed please find below,
1. Subscriber = active cust perform ... - 16:04 Enhancement #6990 (User Acceptance Test): [Bulk Payment] - Validation Error Message Display
- Send to AGRO for SIT/UAT
- 16:02 Change #6931 (Closed - End of life cycle): CR-00062 version 1.0 - Bulk Payment Inquiry Job Enhanc...
- Successfully deployed to Production
Migration ID00068 21/1/2017 - 13:07 Change #6763 (User Acceptance Test): CR-00061 version 1.0 - To amend the placing for Standing Ins...
- Already handover for SIT and UAT on 25/1/2017.
Reminder send on 6/3/2017
Target System handover - 10/3/2017
- 12:53 Task #6332 (User Acceptance Test): Refresh RIB DEMO to latest
- Handover to UAT for testing and sign-off - 3/3/2017
*Target to deploy to Production - 10/3/2017* - 12:50 Task #7066: [CR00063] - Item1. To display all transactions (all status) details on Bulk Payment, ...
- Hi Nisa,
Kindly update on the status of this task.
*Target to be ready for Internal testing is by this Wednesday...
March 02, 2017
- 11:39 Task #7100: [BRS_CR064-1] : Auto Sweeping Setting
- link for BIB: https://172.16.50.27/bib.sit.auto_sweeping/common/Login.do
IBAM link: https://172.16.50.27/ibam.sit.au...
March 01, 2017
- 16:39 Change #6763 (Pending Review): CR-00061 version 1.0 - To amend the placing for Standing Instructi...
- Hi Kak Haida,
Attached is Test Result for this enhancement. Kindly review.
Thank you.
February 28, 2017
- 18:25 Task #7068: [CR00063] - Item3. Email and SMS Notification of Successful and Unsuccessful IB Activ...
- Hi Chee Ping,
Attached sample email provide by User. - 18:23 Task #7208 (Work Completed-End life cycle): [BRS_CR063-Item3] :Email and SMS Notification of Succ...
- Please prepare BRS for this CR and revert to me for review. Thank you.
Below is the related document for your refe... - 18:04 Task #7067: [CR00063] - Item5. Enable Audit Trail of User activities for the company’s
- Hi Steph,
As discussed earlier, kindly proceed on development.
Target to delivered for testing - 12/3/2017 - 17:58 Task #7207 (Prepare BRS): [BRS_CR063-Item5] : Enable Audit Trail of User activities for the compa...
- 17:58 Task #7207 (Work Completed-End life cycle): [BRS_CR063-Item5] : Enable Audit Trail of User activi...
- Please prepare BRS for this CR and revert to me for review. Thank you.
Below is the related document for your refe...
February 27, 2017
- 12:46 Change #6763: CR-00061 version 1.0 - To amend the placing for Standing Instruction Terms & Condit...
- Hi Erni,
Kindly refer Test Result attached.
Thank you. - 12:20 Change #6763: CR-00061 version 1.0 - To amend the placing for Standing Instruction Terms & Condit...
- Erni, kindly check with Akmal on this testing. Please use the Test Script for CR to update the test result. TQ
- 12:16 Change #7044: CR-00055 version 1.4 - ISS Intergration (Batch File)
- Hi Akmal,
Please proceed to verify the report, You may refer to SOW attached. Thank you.
February 23, 2017
- 17:40 Change #7044: CR-00055 version 1.4 - ISS Intergration (Batch File)
- sample reports
February 21, 2017
- 17:34 Change #7044 (Internal Testing): CR-00055 version 1.4 - ISS Intergration (Batch File)
- Finished all the report and passed to Kah Yan to put into SIT server. Please help assign someone to perform internal ...
February 17, 2017
- 14:29 Task #7100: [BRS_CR064-1] : Auto Sweeping Setting
- BRS for Auto Sweeping: https://hub.penril.net/share/s/TepiCHInR_u9nOG3oQaTYA
February 15, 2017
- 18:16 Change #7044 (Development / Work In Progress): CR-00055 version 1.4 - ISS Intergration (Batch File)
- 18:14 Change #7044: CR-00055 version 1.4 - ISS Intergration (Batch File)
- Hi Chee Ping,
LO has been received dated 8/1/2017. We shall start the development. Timeline is as per below:
Deve... - 15:11 Task #7100: [BRS_CR064-1] : Auto Sweeping Setting
- Kah Yan, please help to prepare the BRS for this CR.
- 15:07 Task #7068: [CR00063] - Item3. Email and SMS Notification of Successful and Unsuccessful IB Activ...
- Haida
Please assign back to me, once the sample email and SMS is confirm.
TQ - 11:04 Task #7066: [CR00063] - Item1. To display all transactions (all status) details on Bulk Payment, ...
- Update db script.
- 11:03 Task #7066: [CR00063] - Item1. To display all transactions (all status) details on Bulk Payment, ...
- Add in Kada Enhancement db script.
February 13, 2017
- 16:26 Task #7096: [BRS_CR063-Item1] :To display all transactions (all status) details on Bulk Payment, ...
- Hi kak haida,
Below is the BRS for this CR. Kindly please review. Thank You.
https://hub.penril.net/share/page...