- 17:48 Task #1939: BIB Mock Run data preparation for Internal testing
- Tested FD Placement in BIB: OK
Need to confirm validation on FD account no length - 15:20 Task #1964 (Closed - End of life cycle): BIB: System Demo site - Corporate Admin & Viewer
- To develop the demo site.
- 09:23 Task #1913 (Development / Work In Progress): BIB - Account and Banking:eStatement Download
- Completed. Need confirmation on:
-PDF file naming convention and folder structure
-Login access to file server
February 08, 2013
- 15:45 Task #1939: BIB Mock Run data preparation for Internal testing
- updated mockup data
Mockup not include:
IBAM
- create company
- link/unlink accounts
RIB/BIB
- bill payment
...
February 07, 2013
- 14:51 Task #1775 (Finished Development): BIB-Token Management : Assign token
- 14:50 Task #1775 (Development / Work In Progress): BIB-Token Management : Assign token
- 14:48 Task #1776 (Finished Development): BIB-Token Management : Revoke token
- 14:46 Task #1776 (Development / Work In Progress): BIB-Token Management : Revoke token
- 14:44 Task #1777 (Finished Development): BIB-Token Management : Tag faulty token
- 14:42 Task #1777 (Development / Work In Progress): BIB-Token Management : Tag faulty token
February 05, 2013
- 11:40 Task #1939 (Development / Work In Progress): BIB Mock Run data preparation for Internal testing
February 04, 2013
- 16:14 Task #1939: BIB Mock Run data preparation for Internal testing
- To prepare the mock run data for internal testing: Approaches as below based on modules since we can have some mock r...
- 14:44 Task #1816 (Finished Development): BIB-Fixed Deposit : Token OTP authorization
- 14:43 Task #1818 (Finished Development): BIB-Fixed Deposit :Authorization detail & approval (UP)
- 14:43 Task #1815 (Finished Development): BIB-Fixed Deposit :FD withdrawal
- 14:42 Task #1816 (Development / Work In Progress): BIB-Fixed Deposit : Token OTP authorization
- 14:42 Task #1818 (Development / Work In Progress): BIB-Fixed Deposit :Authorization detail & approval (...
- 14:41 Task #1815 (Development / Work In Progress): BIB-Fixed Deposit :FD withdrawal
- 11:34 Task #1939 (Work Completed-End life cycle): BIB Mock Run data preparation for Internal testing
February 01, 2013
- 15:24 Task #1896 (Finished Development): BIB - Notication Channel (non Transaction)
- 15:23 Task #1895 (Finished Development): BIB - Notication Channel (Transaction)
January 31, 2013
- 15:34 Task #1817 (Finished Development): BIB-Fixed Deposit : Authorization detail & approval (PL)
- 15:33 Task #1737 (Finished Development): BIB-Account Enquiry : Internet banking transaction history
- 15:33 Task #1736 (Finished Development): BIB-Account Enquiry : HOST transaction history
- 15:32 Task #1735 (Finished Development): BIB-Account Enquiry : Account details
- 15:31 Task #1734 (Finished Development): BIB-Account Enquiry : Account summary
January 30, 2013
- 16:09 Task #1913: BIB - Account and Banking:eStatement Download
- reassign to right Anwar...
- 16:04 Task #1768 (Finished Development): BIB-Standing Instruction : Maintenance - delete
- 15:54 Task #1913: BIB - Account and Banking:eStatement Download
- Anwar, please assist.
- 15:47 Task #1771 (Finished Development): BIB-Profile Management : Update profile
- 15:45 Task #1842 (Finished Development): BIB - Store Channel and User Agent into User Transaction Histo...
- 15:38 Task #1771: BIB-Profile Management : Update profile
- shouldn't this change to Finished Development?
- 15:36 Task #1769 (Finished Development): BIB-Standing Instruction : History
- Pending host integration.
- 15:34 Task #1769 (Development / Work In Progress): BIB-Standing Instruction : History
- 13:57 Task #1905 (Development / Work In Progress): BIB-Bulk Transfer:Bulk Enquiry
- The base of its done, now is only pending on the data whether to be read from local database, which then requires mor...
- 10:59 Task #1765 (Finished Development): BIB-Bulk Transfer : Token OTP authorization
January 29, 2013
- 17:32 Task #1766 (Development / Work In Progress): BIB-Bulk Transfer : Authorization detail & approval
- In Approval process, display details upon approval (DONE)
Display confirmation page (DONE)
Build OTP verification f... - 17:30 Task #1765 (Development / Work In Progress): BIB-Bulk Transfer : Token OTP authorization
- Build OTP verification for approver all (DONE)
there is no status FINISH DEVELOPMENT under status, refer to attach... - 15:17 Task #1913 (Dropped-End of life cycle): BIB - Account and Banking:eStatement Download
- Allow the customer to download the statement, this should be apply for CASA account.pls refer to BRS for more informa...
- 15:11 Task #1754 (Finished Development): BIB-Interbank Account Transfer : Token OTP authorization
- Pending Integration
- 15:10 Task #1754 (Development / Work In Progress): BIB-Interbank Account Transfer : Token OTP authoriza...
- 15:00 Task #1755 (Finished Development): BIB-Interbank Account Transfer :Standing Instruction
- Pending Integration
- 14:58 Task #1756 (Finished Development): BIB-Interbank Account Transfer : Authorization detail & approval
- Pending Integration
- 14:57 Task #1764: BIB-Bulk Transfer : MACS bulk file upload
- Provide an upload function for MACS file (DONE)
* remaining: for the without IBG Format not yet since its pending on... - 14:54 Task #1751 (Finished Development): BIB-Interbank Account Transfer : Normal transfer (IBG & RENTAS)
- Pending Integration
- 14:48 Task #1752 (Finished Development): BIB-Interbank Account Transfer : Favourite transfer (IBG & REN...
- Pending Integration
- 09:29 Task #1896: BIB - Notication Channel (non Transaction)
- Tested with JMS
- 09:27 Task #1895: BIB - Notication Channel (Transaction)
- tested with JMS