Activity
From June 12, 2011 to July 11, 2011
July 04, 2011
- 17:02 Task #967: AGROINFRA: PROD Dell Server System Software Installation
- Date : 1/07/2011
Time : 9.00am - 8.00pm
h3. Patch updates :
Patch udpdate for all server successful through ...
June 23, 2011
- 01:32 Task #967: AGROINFRA: PROD Dell Server System Software Installation
- Date : 23/06/2011
Time : 12.00pm - 5.00pm
h3. Hardening done for :
1. ibappdevsvr1
h3. MsSQL(Standard Edi... - 01:18 Task #967: AGROINFRA: PROD Dell Server System Software Installation
- Date : 22/06/2011
Time : 12.00pm - 5.30pm
h3. Set hostname for all server :
*1. ibappdevsvr1*
IP : *10.6.6.20*
Subn...
June 20, 2011
- 12:42 Task #966: AGROINFRA: PROD Dell Server Installation
- Dell EqualLogic installation by Dell Engineer (Mr. Teddy Supriadi) confirmed on 23/6/2011 from 9 AM – 6PM
- 11:57 Task #967: AGROINFRA: PROD Dell Server System Software Installation
- Date : 17/06/2011
Time : 3.00pm - 7.00pm
Window Server 2008 pre-installion done for 14 server.
1. Window Serve...
June 14, 2011
- 19:25 Task #966: AGROINFRA: PROD Dell Server Installation
- Today Activity: Hardware Setup (14/06/2011)
1)Dell rack: PE-4220
2)KVM : 180AS
3)Blade Enclosure (Chassis): PE-M10... - 19:16 Task #966 (Development / Work In Progress): AGROINFRA: PROD Dell Server Installation
June 13, 2011
- 23:54 Task #966: AGROINFRA: PROD Dell Server Installation
- Hardware specs to install on 14/06/2011.
Dell Engineers Information:
1.
Name ... - 23:36 Task #999 (Closed - End of life cycle): AGROINFRA: DR Dell Servers Installation
- 15:13 Task #966: AGROINFRA: PROD Dell Server Installation
- Server hardware rack mounting for Prod scheduled tomorrow - June 14, 2011.
- 09:29 Task #974 (Work Completed-End life cycle): AGROINFRA: Dell Servers Delivery Order Signoff
- compile the packaging slip from DELL (PROD & DRC) and DO from Agrobank-Penril, and get it signed..
Documents are ema...