December 16, 2011
- 10:29 Task #1254 (Work Completed-End life cycle): IBRPRT: RIB User Profile Update Report
- Passed.
- 10:03 Task #1254 (Internal Testing): IBRPRT: RIB User Profile Update Report
- Hi kak ayu,
Fixed by bernard, kindly to be re-test,
thanks...
December 13, 2011
- 15:49 Bug #1282 (Work Completed-End life cycle): RIB Report - Interbank Fund Transfer
- Passed.
- 13:11 Task #1254: IBRPRT: RIB User Profile Update Report
- Report wrongly retrieve the updated time from DB. Still waiting the report to generate in exact time.
TQ. - 13:09 Bug #1282 (Development / Work In Progress): RIB Report - Interbank Fund Transfer
December 12, 2011