Activity

From August 22, 2016 to September 20, 2016

September 20, 2016

18:08 Agrobank Change Request Task #6495 (Work Completed-End life cycle): Preprod Comfort Test ID057
[20/09/2016]
Reviewed as per attached.
Lizahwati Basirun
18:05 Agrobank Change Request Task #6486 (Work Completed-End life cycle): Preprod Comfort Test ID056
[20/09/2016]
Reviewed as per attached.
Lizahwati Basirun
17:29 Agrobank Change Request Enhancement #6379 (Work Completed-End life cycle): BIB Related Issue
Reviewed and updated the test result as attached. Lizahwati Basirun
17:27 Agrobank Change Request Enhancement #6377 (Work Completed-End life cycle): KADA Reported Issues
Reviewed and updated the test result as attached. Lizahwati Basirun
15:32 Agrobank Change Request Task #6369 (Work Completed-End life cycle): Internal Testing Sahabat Agro
[20/09/2016]
Reviewed. Test result has been uploaded into Alfresco in below URL.
https://hub.penril.net/share/s/...
Lizahwati Basirun

August 25, 2016

15:31 Agrobank Change Request Task #6367 (Work Completed-End life cycle): AgroBank Bulk Payment CR Upload Encrypted file
Issues has been tested and pass Erni Suhaireen Zulkifli
 

Also available in: Atom