Activity
From December 07, 2021 to January 05, 2022
January 05, 2022
- 17:01 CR20015 - FRIA TD Placement Bug #12739 (Internal Testing): [Internal Testing] RIB_Term Deposit Placement: System loading with...
- *Steps to reproduce:*
# Perform TD Placement.
# At Confirm page, Input invalid TAC.
# After hit error, input valid...
December 28, 2021
- 17:20 CR20015 - FRIA TD Placement Bug #12646 (Work Completed-End life cycle): [Internal Testing] Term Deposit Placement_New Placeme...
- Tested & passed.
Thank you. - 17:19 CR20015 - FRIA TD Placement Bug #12715 (Work Completed-End life cycle): [Internal Testing] IBAM_RIB Report: to display proper...
- Tested & passed for both RIB and BIB.
Thank you. - 16:34 CR20015 - FRIA TD Placement Bug #12715 (Internal Testing): [Internal Testing] IBAM_RIB Report: to display proper reason for u...
- Hi Kak Akmal,
Kindly redownload and verify the RIB report for date 01/12/2021 - 11:41 CR20015 - FRIA TD Placement Bug #12715 (Work Completed-End life cycle): [Internal Testing] IBAM_RIB Report: to display proper...
- Hi Bal,
Currently Reason displayed as "Transaction is"
Request to display full sentence at reason field.
December 09, 2021
- 15:13 CR20015 - FRIA TD Placement Bug #12671 (Work Completed-End life cycle): [Internal Testing] RIB_Term Deposit Withdrawal: All f...
- Tested and passed.
Thank you. - 14:34 CR20015 - FRIA TD Placement Bug #12646 (Internal Testing): [Internal Testing] Term Deposit Placement_New Placement : Able to ...
- Hi Kak Akmal,
Kindly retest this scenario, kak Ilah just inform me the issue have been fixed.
- 14:33 CR20015 - FRIA TD Placement Bug #12671 (Internal Testing): [Internal Testing] RIB_Term Deposit Withdrawal: All fields were no...
- Hi akmal.
Kindly retest this scenario, I have already deployed the fixes
December 08, 2021
- 12:18 CR20015 - FRIA TD Placement Bug #12659 (Work Completed-End life cycle): [Internal Testing] BIB_Term Deposit Placement: All fi...
- Tested & passed.
Thank you. - 12:17 CR20015 - FRIA TD Placement Bug #12671 (Work Completed-End life cycle): [Internal Testing] RIB_Term Deposit Withdrawal: All f...
- *Step to reproduce:*
1. Perform TD withdrawal until result page.
2. Click on Make Another Transaction button
*...
Also available in: Atom