June 21, 2016
- 14:14 Enhancement #6374 (Closed - End of life cycle): [Internal Testing] Takaful Payment for RIB and BIB
- Dear Akmal,
Kindly assist to do the internal testing for this CR. The testing should be included as below modules....
June 15, 2016
- 15:20 Task #6339: CMS :Takaful Payment: prepare test script for RIB & BIB
- pls assist add on for BIB also. If possible, try add on more scenario like for same person, can allow to buy more th...
June 14, 2016
- 12:16 Task #6339: CMS :Takaful Payment: prepare test script for RIB & BIB
- Attached is Test Script for "Takaful Payment" module based on current BRS.
Since it have some update, will update on...
June 13, 2016
June 10, 2016
- 11:48 Task #6339 (Work Completed-End life cycle): CMS :Takaful Payment: prepare test script for RIB & BIB
- Hi Akmal,
As disc, you will assist on the testing and prepare the test script for the Takaful Sales module.