Activity

From May 16, 2010 to June 14, 2010

June 14, 2010

Avatar?id=1733&size=24 15:45 Task #71 (Development / Work In Progress): BV Tuning (Base on JBoss4.0.5)
Tuning Parameter affected
1)Development mode - Off - ok
2)Hot Deployment mode - Off - ok
3)Remove FARM - ok
4)L...
Ahmad Hazri
Avatar?id=1733&size=24 10:47 Task #71: BV Tuning (Base on JBoss4.0.5)
* Failed to install BV81 in CentOS 5.4 [RHEL 5.4]
* Change to CentOS 4.8 platform [Red Hat Enterprise Linux 4.8] si...
Ahmad Hazri

June 10, 2010

Avatar?id=1733&size=24 12:05 Document: CSI #
End user CSI # for Oracle Customer Ahmad Hazri
Avatar?id=1733&size=24 12:05 CSI__23.pdf
Ahmad Hazri

June 08, 2010

Avatar?id=1733&size=24 10:22 Task #13 (Closed - End of life cycle): Redmine SMTP server setup
Ahmad Hazri

June 04, 2010

Avatar?id=1733&size=24 10:57 Task #71: BV Tuning (Base on JBoss4.0.5)
1. Installing Oracle DB in CentOS 5
2. Creating schema.
Ahmad Hazri
Avatar?id=1733&size=24 10:55 Task #71 (Closed - End of life cycle): BV Tuning (Base on JBoss4.0.5)
Preparing the tuning parameter for JBoss Application Server (4.0.5)
Ahmad Hazri

June 01, 2010

Avatar?id=1733&size=24 14:55 Task #16: WebSphere Application Server Deep Dive 25 May - 27 May
Done! Ahmad Hazri
Avatar?id=1733&size=24 14:26 redmine_gmailSMTP_setup.txt
Ahmad Hazri
Avatar?id=1733&size=24 14:11 Task #13: Redmine SMTP server setup
Done.
attached is the guide
Ahmad Hazri

May 31, 2010

Avatar?id=1733&size=24 15:19 Task #13: Redmine SMTP server setup
Using different Email server
* streamyx email
* gmail
both failed. need to debug.
Ahmad Hazri
11:42 Task #16: WebSphere Application Server Deep Dive 25 May - 27 May
Please update your status Tan Lee Yong

May 24, 2010

Avatar?id=1733&size=24 11:03 Task #16 (Closed - End of life cycle): WebSphere Application Server Deep Dive 25 May - 27 May
Training and Preparation for WAS7 Certification Ahmad Hazri
Avatar?id=1733&size=24 11:01 Task #15 (Closed - End of life cycle): IBM DB2 Database on VMWare Workstation
To create an IBM DB2 Database on VMWAre Workstation for any Development project. Ahmad Hazri
Avatar?id=1733&size=24 11:00 Task #14 (Closed - End of life cycle): Oracle DB on VMWare Workstation
To create an Oracle DB VMWAre Workstation for any Development project. Ahmad Hazri
Avatar?id=1733&size=24 10:40 Task #13 (Closed - End of life cycle): Redmine SMTP server setup
To configure Redmine SMTP server which use to send any email to all members. Ahmad Hazri
 