June 22, 2016

Avatar?id=2607&size=24 20:56 Task #6314 (Pending Customer Feedback): [Mortgage] - FSD
Today, I have sent the translations table needs to be filled up by user, as per requested by Bu Melie. I asked her ab... Rayvandy Gabbytian

June 16, 2016

Avatar?id=2607&size=24 17:40 Task #6311: M2U: BPJS
Mr. Tan,
Questions to the bank are not yet answered. Highlighted these to Thomas during OPG meeting:
1. Bank to...
Rayvandy Gabbytian
16:30 Task #6362 (Closed - End of life cycle): OPG: SIT Test Script
Hi Tommy, test through the OPG and create test script with test result. Tan Lee Yong
16:27 Task #6311: M2U: BPJS
Hi Tommy,
What is the update on this ? Past the due date.
Tan Lee Yong

June 14, 2016

Avatar?id=1966&size=24 17:41 Task #6312 (Internal Testing): RMBP: BPJS
Hi Tommy,
Please refer my email get bii_Restful war file and help to deploy to SIT environment and please use bran...
Ngoh Chee Onn
Avatar?id=1966&size=24 09:17 Task #6312: RMBP: BPJS
Left BPJS fav bill payment. Ngoh Chee Onn

June 13, 2016

09:40 Task #6310: RMBP: Build RMBP with Worklight 6.3
APK successfully Compiled. Issue already fixed, tested by user
IPA currently still fail, Update by Gabby
Aditya Prathama

June 09, 2016

16:29 Task #6314: [Mortgage] - FSD
Since Gabby still not yet start this FSD, need to move on.
Amy, please help to complete this FSD.
Tan Lee Yong
10:22 Task #6310 (Development / Work In Progress): RMBP: Build RMBP with Worklight 6.3
Tan Lee Yong

June 08, 2016

Avatar?id=1966&size=24 19:03 Task #6312: RMBP: BPJS
Complete separate payee from details to step 2 and finish details page.
Ngoh Chee Onn
13:11 Task #6310: RMBP: Build RMBP with Worklight 6.3
APK WLAPP Build Success for SIT server Aditya Prathama

June 07, 2016

18:25 Task #6310: RMBP: Build RMBP with Worklight 6.3
IDE on Windows Installed with MobileFirst 6.3. Still failed to start local server. Aditya Prathama

June 06, 2016

14:36 Task #6314 (Closed - End of life cycle): [Mortgage] - FSD
Create the FSD based on the user requirements (BRD):
https://hub.penril.net/share/s/gyMtln0aTs2taERbrY2m-A
Tan Lee Yong
14:32 Task #6313 (Closed - End of life cycle): [Wealth Management] - Development
Resource Arrangement:-
Development: Chee Onn
Bug fixes: Chee Onn
Internal Testing = Tommy
Prepare Test Scriot = T...
Tan Lee Yong
14:31 Task #6311: M2U: BPJS
Resource Arrangement:-
Development: Chee Onn
Bug fixes: Chee Onn
Internal Testing = Tommy
Prepare Test Scriot = T...
Tan Lee Yong
14:30 Task #6309: RMBP: Wealth Management
Tan Lee Yong wrote:
> To develop Wealth Management on RMPB
>
> BRS:
> https://hub.penril.net/share/s/GwUWOJjUQWq...
Tan Lee Yong
14:28 Task #6312 (Closed - End of life cycle): RMBP: BPJS
Resource Arrangement:-
Development: Chee Onn
Bug fixes: Chee Onn
Internal Testing = Tommy
Prepare Test Scriot = T...
Tan Lee Yong
14:25 Task #6311 (Internal Testing): M2U: BPJS
Hi Gabby,
Please follow up with Wahyu on the host readiness for our development test.
Tan Lee Yong
14:24 Task #6311 (Closed - End of life cycle): M2U: BPJS
Development: Completed
Deploy to SIT: Completed
Create Test Script: Completed
SIT: Pending
UAT: TBA
Go Life: TBA
Tan Lee Yong
14:19 Task #6310 (Closed - End of life cycle): RMBP: Build RMBP with Worklight 6.3
Due to 6.0 slowness on certain devices, Wahyu saying that Worklight 6.3 will solve this problem. So, require to build... Tan Lee Yong
14:18 Task #6309 (Closed - End of life cycle): RMBP: Wealth Management
To develop Wealth Management on RMPB
BRS:
https://hub.penril.net/share/s/GwUWOJjUQWqYjXuoM5thJw
Tan Lee Yong
 