September 11, 2014

18:02 Task #4663 (Finished Development): Change notification mode:
Updated Business logic Ong Wei Kuan
18:01 Task #4665 (Finished Development): Batch Process:User Activation
Updated batch process activation, only shown for Batch Email/Batch SMS Ong Wei Kuan
16:03 Task #4665 (Development / Work In Progress): Batch Process:User Activation
Wrongly update. Still working in progress. Ong Wei Kuan
15:59 Task #4665 (Finished Development): Batch Process:User Activation
Script to update corporate id to dummy and script to update cif no to dummy were delivered. Ong Wei Kuan

September 05, 2014

14:12 Task #4663 (Development / Work In Progress): Change notification mode:
-Update the business logic for change notification mode by following the FSD Appendix A.
-Not yet branch out, will ...
Ong Wei Kuan
 

Also available in: Atom