June 11, 2021

09:45 Enhancement #11570 (System Integration Test): CR EPF Late/Other Payment EOD parameter changes
Send to SIT on 8/6/21 Nurul Athira Abdul Rahim

June 09, 2021

13:09 Enhancement #11570 (Internal Testing): CR EPF Late/Other Payment EOD parameter changes
EPF Other payment validation has been updated. Kindly retest. Nurul Hasnieza Bt Mohd Zamri

June 08, 2021

17:10 Enhancement #11570 (Development / Work In Progress): CR EPF Late/Other Payment EOD parameter changes
Hi Hasnieza, please update the Form F reference no field:
Currently : System accept all char include special ch...
Nurul Athira Abdul Rahim
 