Activity

From September 03, 2021 to October 02, 2021

September 29, 2021

15:42 Enhancement #11570: CR EPF Late/Other Payment EOD parameter changes
28/9/21 - Azyan
SIT has been tested and pass. However, we unable to proceed to UAT (ICBS 6.4) since we need to go ...
Nurul Athira Abdul Rahim

September 27, 2021

11:59 Enhancement #11570 (User Acceptance Test): CR EPF Late/Other Payment EOD parameter changes
Nurul Athira Abdul Rahim

September 24, 2021

15:11 Change #11264 (User Acceptance Test): [SCP ID :##5559##] : Daily balance summary >> CR20002
Nurul Athira Abdul Rahim

September 03, 2021

18:05 Enhancement #11570 (Internal Testing): CR EPF Late/Other Payment EOD parameter changes
SIT has been deployed. Kindly retest.
-EPF Other History Listing
-EPF Other Cancel file
-Reverse file processing...
Nurul Hasnieza Bt Mohd Zamri
 

Also available in: Atom