Activity

From April 22, 2011 to May 21, 2011

May 05, 2011

Avatar?id=1733&size=24 11:34 Task #839 (Closed - End of life cycle): Project Time Frame
Ahmad Hazri

April 27, 2011

16:25 Task #839: Project Time Frame
session fail-over not working as some of the objects we stored in the session is not serialized. Turn off the session... Ang Wei Cheng

April 25, 2011

Avatar?id=1733&size=24 17:49 Task #839: Project Time Frame
im guessing.. - could be the sticky session.
continue on Wednesday.
Ahmad Hazri
Avatar?id=1733&size=24 17:46 Task #839: Project Time Frame
WAS Clustering setup successfully.
Now issue on RIB & RSS, after success to login, cannot do anything as the brows...
Ahmad Hazri
Avatar?id=1733&size=24 15:54 Task #839: Project Time Frame
WAS Clustering (Pre-configuration)
Server: T2 & T3
Prerequisite:
1)Date & Time should 5 minutes different for ...
Ahmad Hazri
Avatar?id=1733&size=24 15:39 Task #839 (Development / Work In Progress): Project Time Frame
Ahmad Hazri
 