Activity
From May 29, 2016 to June 27, 2016
June 24, 2016
- 16:26 Task #6320: [Internal Testing] CMS Labuan FTT (Additional Request)
- Dear Kak Lizah,
Attached updated Test Result.
Thank you.
June 09, 2016
- 11:47 Task #6320: [Internal Testing] CMS Labuan FTT (Additional Request)
- Dear Kak Lizah,
Successfully tested.
Thank you.
June 08, 2016
- 14:07 Enhancement #4782: IBSCR073 - Logger Enhancement (CMS Labuan)
- Migration failed. Need to reschedule for migration.
June 07, 2016
- 13:17 Task #6320 (Work Completed-End life cycle): [Internal Testing] CMS Labuan FTT (Additional Request)
- Dear Akmal,
Kindly assist to do the internal testing for this CR which is to test on the FTT module. Please do ref...
June 06, 2016
- 13:51 Change #6308 (Internal Testing): IBSCR079 - CMS Labuan FTT (Additional Request)
- 13:51 Change #6308 (Work Completed-End life cycle): IBSCR079 - CMS Labuan FTT (Additional Request)
- 1)To add Instructed Amount in CMS Labuan at Transaction Details information.
This field to tag to Swift field 33B.
...
Also available in: Atom