Activity
From January 14, 2011 to February 12, 2011
February 11, 2011
- 17:48 Change #783 (Development / Work In Progress): IBSCR026 - GIA Upliftment Trxn Code 176
- Under development for CIB n BIB.
Refer to : http://hub.penril.net/redmine/projects/kfh-ibscr026 - 17:27 Change #783 (Closed - End of life cycle): IBSCR026 - GIA Upliftment Trxn Code 176
- Modify GIA Upliftment to only perform single SP trxn code 176
Start development Tuesday n Friday, scheduled to be ...
January 14, 2011
- 16:37 Change #717 (User Acceptance Test): IBSCR025 - KFH New Branch Opening
- Migrated to STG on 12/01/2011
- 16:33 Feature #668 (Development / Work In Progress): IBSCR024 - 3+8 Mobile Number
- Development completed
Pending migration to STG because Chooi wanted to hold the migration first, to let SMS UAT comp...
Also available in: Atom