17:40 Task #5290: [Documentation]_BRS for IBSCR072 - Payment Reference
Hi Akmal,
Reviewed. Kindly updated the document as per highlighted.
Norhaidah Md Dasuki

May 12, 2015

16:59 Task #5290 (Development / Work In Progress): [Documentation]_BRS for IBSCR072 - Payment Reference
Hi Kak Haida,
Kindly review attached BRS.
For CORUS & BVMC parts will be updated later.
Thank you.
Nurul Akmal
10:20 Task #5170: IBSCR074 - Basic Functionality Test Script for GST
Akmal,
Please update the status. TQ
Norhaidah Md Dasuki

May 11, 2015

12:35 Task #5290: [Documentation]_BRS for IBSCR072 - Payment Reference
Hi Akmal,
Please update the progress and upload the 1st draft for review by tomorrow 4pm.
Norhaidah Md Dasuki

April 29, 2015

17:31 Task #5286: [Conditional Sign-off Issue]_IBSCR #068, #072 & #074
Check in the system
CIB and BIB:
3rd Party and FTT allow ',' for both open and register transactions
Yap Kah Yan

April 28, 2015

12:59 Task #5290 (Work Completed-End life cycle): [Documentation]_BRS for IBSCR072 - Payment Reference
To compile all changes with regards to Payment Reference request details.
1. BRS write-up based on User request deta...
Norhaidah Md Dasuki

April 27, 2015

17:35 Change #4818 (Closed - End of life cycle): IBSCR072 - Payment Reference (Channel type 1-KFHOnline...
Norhaidah Md Dasuki
17:31 Task #5286 (Work Completed-End life cycle): [Conditional Sign-off Issue]_IBSCR #068, #072 & #074
To fix on Conditional Sign-off Issue for below CR:
# IBSCR068 & 72 - IBG Enhancement/Payment Reference
# IBSCR074 -...
Norhaidah Md Dasuki
17:21 Change #5148 (Closed - End of life cycle): IBSCR074 - GST
Work Completed - Test full-cycle on basic functionality.
Deployed to PRODUCTION at 17/04/2015 with Conditional Sign-...
Norhaidah Md Dasuki
17:19 Enhancement #5215 (Closed - End of life cycle): URF-14-12-163: IBG-009
Treat as new CR. Norhaidah Md Dasuki
17:18 Enhancement #4719 (Pending UAT Deployment): IBSCR070 - IBG EPF Direct Crediting (Batch Date & EPF...
Still Pending on UAT Deployment and test plan. Norhaidah Md Dasuki
17:16 Change #4832 (Closed - End of life cycle): IBSCR068 - IBG Enhancement (Financing Repayment, Retur...
Norhaidah Md Dasuki
17:12 Task #5242 (Closed - End of life cycle): [Vendor SIT]_IBSCR074: Corus for GST
Work Completed - Test full-cycle on basic functionality.
Deployed to PRODUCTION at 17/04/2015.
Norhaidah Md Dasuki
17:11 Task #5152 (Closed - End of life cycle): IBSCR074 - CORUS: GST Implementation
Norhaidah Md Dasuki
17:07 Task #5241 (Closed - End of life cycle): [Vendor SIT]_IBSCR074: BVMC for GST
Work Completed - Test full-cycle on basic functionality.
Deployed to Production at 17/04/2015.
Norhaidah Md Dasuki
17:05 Task #5230 (Closed - End of life cycle): IBSCR074 - GST Implementation for CIB - Stop Cheque
Work Completed and successfully.
Deployed to Production at 17/04/2015.
Norhaidah Md Dasuki
17:04 Task #5171 (Closed - End of life cycle): [Vendor SIT]_IBSCR074: GST for CIB
Deployed to Production at 17/04/2015. Norhaidah Md Dasuki

April 23, 2015

12:30 Task #5169 (Closed - End of life cycle): IBSCR074 - IBG Service for GST Implementation
Already migrate to production Hafizudin MD
12:27 Change #4832 (Finished Development): IBSCR068 - IBG Enhancement (Financing Repayment, Return Mess...
migation to prod successful Hafizudin MD
12:25 Task #5243 (Closed - End of life cycle): [Vendor SIT]_IBSCR074: IBG Service for GST Implementation
deploy successful Hafizudin MD
 