May 28, 2015
- 16:03 Task #5170 (Work Completed-End life cycle): IBSCR074 - Basic Functionality Test Script for GST
- Document has been uploaded in alfresco.
Deployed to Production at 17/04/2015. - 13:35 Task #5290 (Pending Review): [Documentation]_BRS for IBSCR072 - Payment Reference
- Hi Kak Aida,
Attached is updated BRS.
Kindly review.
Thank you.
May 18, 2015
- 17:40 Task #5290: [Documentation]_BRS for IBSCR072 - Payment Reference
- Hi Akmal,
Reviewed. Kindly updated the document as per highlighted.
May 12, 2015
- 16:59 Task #5290 (Development / Work In Progress): [Documentation]_BRS for IBSCR072 - Payment Reference
- Hi Kak Haida,
Kindly review attached BRS.
For CORUS & BVMC parts will be updated later.
Thank you.
- 10:20 Task #5170: IBSCR074 - Basic Functionality Test Script for GST
- Akmal,
Please update the status. TQ
May 11, 2015
- 12:35 Task #5290: [Documentation]_BRS for IBSCR072 - Payment Reference
- Hi Akmal,
Please update the progress and upload the 1st draft for review by tomorrow 4pm.