Activity

From December 06, 2017 to January 04, 2018

January 03, 2018

16:15 Task #6713 (Dropped-End of life cycle): CR:Transaction Limit for Exempted Non-resident
Dropped since no update/feedback from customer. Lizahwati Basirun
16:12 Task #5704 (Pending Prod Deployment): IBSCR078 - FTT and RENTAS Store Procedures
Migrated to Production on 2nd Nov 2017 but only for RENTAS Lizahwati Basirun
14:49 Change #8164 (Work Completed-End life cycle): [Change Request] - IBSCR087 Separating the integrat...
Scope of work is a below:-
1) Separate out the integration from ESB to new webservice application and deploy to IB...
Lizahwati Basirun

January 02, 2018

09:33 Change #8050: [Change Request] - IBSCR098 Payment advise from IBG Core to KFH PowerCard system to...
Awaiting Hps feedback regarding authentication failed. Tan Jeng Wei
 