March 02, 2020
- 10:51 Task #10660: [Source Code Retrofitting] Merging 2FA into RPP Phase 2 branch
- updated start date as VAPT ends at 3rd March
February 25, 2020
- 11:19 Change #8050 (Work Completed-End life cycle): [Change Request] - IBSCR098 Payment advise from IBG...
- Migrated to production on October 11th 2019.
- 10:59 Task #10592 (Work Completed-End life cycle): [Documentation] Technical Document for Stronger 2FA
- Delivered to KFH IT on February 19th 2020
- 10:03 Task #10660 (Work Completed-End life cycle): [Source Code Retrofitting] Merging 2FA into RPP Phas...
- Dear Kahyan,
Kindly assist to merge the source code for 2FA into RPP Phase 2. Please help to ensure the source cod...