May 27, 2015
- 17:55 Task #5157: Logger Enhancement - BIB
- Hi Akmal,
Kindly proceed to do Internal Testing on positive and negative scenario. For positive test, please ensure ... - 17:17 Task #5157 (Internal Testing): Logger Enhancement - BIB
- BIB enhance logger Successfully Deploy on KFHIB09:7110/kfh_bib_logger_positive
- 15:47 Task #5157: Logger Enhancement - BIB
- Deployed on development server, but got error while login. checking the root cause
May 26, 2015
- 17:25 Task #5157: Logger Enhancement - BIB
- Updated logger enhancement to add in more features as below:
Log Any Exceptions to database into "IB_ERROR_EXCEPTI... - 15:16 Task #5156: Logger Enhancement - CIB
- Updated logger enhancement to add in more features as below:
# Log Any Exceptions to database into "IB_ERROR_EXCEP... - 11:07 Task #5157: Logger Enhancement - BIB
- All Code for BIB logger done, BIB Logger need update some code from cheeping.
- 09:36 Task #5157: Logger Enhancement - BIB
- Aditya, kindly update the status by 11:00am today. We need to start the internal testing immediately.
May 25, 2015
- 16:31 Task #5156: Logger Enhancement - CIB
- Hi Ayu,
Kindly proceed to do Internal Testing on positive and negative scenario. For positive test, please ensure it... - 16:07 Task #5156 (Internal Testing): Logger Enhancement - CIB
- code deployed at kfh_costumer_prd_gst instance on development server.
May 21, 2015
- 15:04 Task #5321 (User Acceptance Test): KFH SMSCron Enhancement Test
- Hi Chee Ping,
Internal test completed. Please proceed to pass to KFH (IT) for further action. Attached is the revi... - 11:24 Task #5321 (Pending Review): KFH SMSCron Enhancement Test
- Dear Kak Haida,
Successfully tested.
Test Result attached.
Thank you.
May 19, 2015
- 14:29 Task #5321 (Work Completed-End life cycle): KFH SMSCron Enhancement Test
- Test environment setup and scenario:-
1) SD run 2 SMSCron service (point to staging DB) and let it run forever
2) Q...
May 18, 2015
- 17:40 KFH Change Request Task #5290: [Documentation]_BRS for IBSCR072 - Payment Reference
- Hi Akmal,
Reviewed. Kindly updated the document as per highlighted.
May 12, 2015
- 16:59 KFH Change Request Task #5290 (Development / Work In Progress): [Documentation]_BRS for IBSCR072 - Payment Reference
- Hi Kak Haida,
Kindly review attached BRS.
For CORUS & BVMC parts will be updated later.
Thank you.
- 11:14 Task #5157 (Pending SIT Deployment): Logger Enhancement - BIB
- Hi Aditya,
Please assist to deploy to staging in order for QA to proceed with testing.
Kah Yan,
Kindly assist Ad... - 11:13 Task #5156 (Pending SIT Deployment): Logger Enhancement - CIB
- Hi Aditya,
Please assist to deploy to staging in order for QA to proceed with testing.
Kah Yan,
Kindly assist A... - 10:20 KFH Change Request Task #5170: IBSCR074 - Basic Functionality Test Script for GST
- Akmal,
Please update the status. TQ
May 11, 2015
- 12:35 KFH Change Request Task #5290: [Documentation]_BRS for IBSCR072 - Payment Reference
- Hi Akmal,
Please update the progress and upload the 1st draft for review by tomorrow 4pm.
April 29, 2015
- 17:31 KFH Change Request Task #5286: [Conditional Sign-off Issue]_IBSCR #068, #072 & #074
- Check in the system
CIB and BIB:
3rd Party and FTT allow ',' for both open and register transactions
April 28, 2015
- 12:59 KFH Change Request Task #5290 (Work Completed-End life cycle): [Documentation]_BRS for IBSCR072 - Payment Reference
- To compile all changes with regards to Payment Reference request details.
1. BRS write-up based on User request deta...