February 12, 2018
- 14:01 KFH Change Request Change #8050: [Change Request] - IBSCR098 Payment advise from IBG Core to KFH PowerCard system to...
- Hi Lizah,
Web Service down again, i not able to test. - 10:53 KFH Change Request Change #8050: [Change Request] - IBSCR098 Payment advise from IBG Core to KFH PowerCard system to...
- Dear Jeng Wei,
What is the status on this CR?
January 29, 2018
- 10:33 KFH Change Request Change #8050 (Development / Work In Progress): [Change Request] - IBSCR098 Payment advise from IB...
- Dear Jeng Wei,
Please update the status on this CR and ensure this CR completed by Feb 9th.
Thank you. - 10:19 KFH Change Request Change #8164 (Work Completed-End life cycle): [Change Request] - IBSCR087 Separating the integrat...
- CR Done. Migrated to production on 20012018