Activity
From April 22, 2019 to May 21, 2019
May 21, 2019
- 12:54 KFH Change Request Enhancement #8752 (Work Completed-End life cycle): [Change Request] IBSCR111 - Item 3 : Implement...
- Migrated to production on 26/04/2019 - 1200am (Friday)
- 12:53 KFH Change Request Enhancement #8767 (Work Completed-End life cycle): [Change Request] IBSCR111 - Item 2 : Require ...
- Migrated to production on 26/04/2019 - 1200am (Friday)
- 12:53 KFH Change Request Enhancement #8770 (Work Completed-End life cycle): [Change Request] IBSCR111 - Item 1 : To enhanc...
- Migrated to production on 26/04/2019 - 1200am (Friday)
- 12:52 KFH Change Request Task #8796 (Work Completed-End life cycle): [IBSCR111 : Item 5] To add transaction signing for tr...
- Migrated to production on 26/04/2019 - 1200am (Friday)
- 12:51 KFH Change Request Enhancement #8769 (Work Completed-End life cycle): [Change Request] IBSCR111 - Item 4 : Implement...
- Migrated to production on 26/04/2019 - 1200am (Friday)
April 23, 2019
- 18:06 Task #9858 (Development / Work In Progress): [FSD_IBSCR113] Retail Payments Platform (RPP) - Inte...
- FSD for KFHOnline has been uploaded to alfresco.
URL: https://hub.penril.net/share/page/site/kfh/document-details?n...
Also available in: Atom