Activity
From February 01, 2020 to March 01, 2020
February 25, 2020
- 11:19 KFH Change Request Change #8050 (Work Completed-End life cycle): [Change Request] - IBSCR098 Payment advise from IBG...
- Migrated to production on October 11th 2019.
- 10:59 KFH Change Request Task #10592 (Work Completed-End life cycle): [Documentation] Technical Document for Stronger 2FA
- Delivered to KFH IT on February 19th 2020
- 10:03 KFH Change Request Task #10660 (Work Completed-End life cycle): [Source Code Retrofitting] Merging 2FA into RPP Phas...
- Dear Kahyan,
Kindly assist to merge the source code for 2FA into RPP Phase 2. Please help to ensure the source cod...
Also available in: Atom