October 22, 2010

19:07 Bug #439 (Closed - End of life cycle): BCA-DDA-UAT-C021
Issue closed by Chooi So Fun on 19.10.10 Latipah Abdul Rashid
19:06 Bug #437 (Closed - End of life cycle): BCA-DDA-UAT-C019
Issue closed by Chooi So Fun on 19.10.10 Latipah Abdul Rashid
15:08 Bug #554 (Development / Work In Progress): Banker's Cheque Application step 2/5 15/10/2010
change status to work in progress Hafizudin MD
11:59 Bug #554: Banker's Cheque Application step 2/5 15/10/2010
Please provide status update once get this message. Tan Lee Yong

October 18, 2010

14:49 Bug #437: BCA-DDA-UAT-C019
tested by hafiz
status ok
Hafizudin MD

October 15, 2010

16:04 Bug #439: BCA-DDA-UAT-C021
tested by hafiz Hafizudin MD
15:07 Bug #554 (Work Completed-End life cycle): Banker's Cheque Application step 2/5 15/10/2010
bug at step 2/5
- Applicant's NRIC / Passport No. with space at the back
- Applicant's NRIC / Passport No. with und...
Hafizudin MD

October 06, 2010

12:11 Bug #437 (Work Completed-End life cycle): BCA-DDA-UAT-C019
Change “Estimated Comission” to “Estimated Commission” Siti Norahayu Mohd Desa
12:10 Bug #439: BCA-DDA-UAT-C021
Change “Estimated Comission” to “Estimated Commission” Siti Norahayu Mohd Desa
12:09 Bug #439 (Work Completed-End life cycle): BCA-DDA-UAT-C021
Change “Estimated Comission” to “Estimated Commission” Siti Norahayu Mohd Desa

October 04, 2010

19:34 Bug #439 (Development / Work In Progress): BCA-DDA-UAT-C021
Status update by Chooi So Fun on 04/10/2010:
Fail - Change “Estimated Comission” to “Estimated Commission”
Latipah Abdul Rashid
19:28 Bug #437 (New - Begin Life Cycle): BCA-DDA-UAT-C019
Status update by Chooi So Fun on 04/10/2010:
Fail - refer to file attached for details on the amendments
Latipah Abdul Rashid
 