Activity

From July 31, 2010 to August 29, 2010

August 17, 2010

16:50 Task #403 (Work Completed-End life cycle): Update CIB SecuredMailbox BRS v1.0
Finish updated all the CIB screen shots in SecuredMailbox BRS. Ngoh Chee Ping
14:58 Task #293 (Closed - End of life cycle): CIB Sent box
Tan Lee Yong
14:57 Task #292 (Closed - End of life cycle): CIB Trash box
Tan Lee Yong
14:16 Task #403 (Closed - End of life cycle): Update CIB SecuredMailbox BRS v1.0
Update the CIB BRS to the most updated screen shot Tan Lee Yong

August 03, 2010

09:44 Task #312 (Work Completed-End life cycle): Prepare UAT Test Script for CIB Secured Mailbox
Version 2.0 = CIB_SecuredMailbox_Test_Script_v2.0.xls Nandong Frank

August 02, 2010

17:32 Task #312: Prepare UAT Test Script for CIB Secured Mailbox
Check again if got missing Nandong Frank
17:28 Task #312: Prepare UAT Test Script for CIB Secured Mailbox
listing all based on CIB Secure Mailbox for Testing in UAT Nandong Frank
 