Activity

From August 30, 2010 to September 28, 2010

September 24, 2010

17:18 Task #242 (Development / Work In Progress): Migration Plan for SMS Notification & Remittance Appl...
Tan Lee Yong

September 21, 2010

17:30 Task #242: Migration Plan for SMS Notification & Remittance Application Form
# Updated list of migration files
# Added list of migration files for IBUtils.jar (contents which were changed)
Wong Bernard

September 20, 2010

17:31 Task #242: Migration Plan for SMS Notification & Remittance Application Form
# Prepared list of migration files
# Perepared summary file of changes required to be performed
# Migration plan do...
Wong Bernard

September 13, 2010

18:07 Task #180 (Closed - End of life cycle): Test Script for report
Tan Lee Yong
 

Also available in: Atom