16:32 Task #814 (Internal Testing): Company Module
fixing bugs:
1. validation message
2. back button location
Wijayanti Nitya
16:26 Task #818 (System Integration Test): SMS Integration
Completed development and pending SIT test on 11th April 2011 Cheang Danniell
16:26 Task #838 (Internal Testing): Customer Enquiry Module
Please test customer enquiry module for:
1. Search user
2. Delete user
3. Enable user (when user status is disabl...
Wijayanti Nitya
16:25 Task #827 (Pending Review): Data Import Module for User Migration
Cheang Danniell
16:24 Task #819 (System Integration Test): Custody Finalizes Interface
Completed discussion and pending for SIT next Monday on 11th April 2011 Cheang Danniell
16:22 Task #817 (Pending Customer Feedback): Add DB Tables
Designed tables for cas Cheang Danniell
16:20 Task #820 (Pending Customer Feedback): New Interfaces Development
Added CAS API WS to cater for business rules Cheang Danniell
16:19 Task #822 (Pending Customer Feedback): Authentication Module Customization
Added CAS WS API to meet business requirements. Cheang Danniell
16:17 Task #825 (Pending Customer Feedback): Audit Log - Before & After Update Detail
Added snapshots for each activity done via CAS Administration in Audit Log Module Cheang Danniell
16:15 Task #826 (Work Completed-End life cycle): User Status Update Module
Cheang Danniell
16:14 Task #826: User Status Update Module
Program to change status daily based on following business rules:
New, Active users: check for dormant period, if re...
Cheang Danniell
16:14 Task #838 (Development / Work In Progress): Customer Enquiry Module
Done customer enquiry module:
- Search
- Delete
- Enable
- Disable
- Assign Token
- Remove Token
- Enable T...
Wijayanti Nitya
16:11 Task #838 (Closed - End of life cycle): Customer Enquiry Module
Development of this module, assign to quality engineer for testing once completed Cheang Danniell
15:58 Task #814: Company Module
Tested by hafiz
status : failed
1) please add space to this error - Company Name cannot include special characte...
Hafizudin MD
15:41 Task #821 (Internal Testing): Change Authentication Mode
Wijayanti Nitya
15:33 Task #816 (Work Completed-End life cycle): Token Module
Tested by Hafiz
Status Passed
Hafizudin MD
10:56 Task #815 (Internal Testing): Batch Module
already done by Daniell Wijayanti Nitya

April 07, 2011

17:40 Task #816: Token Module
please use dev server to test it, and pull the latest code.
Database:
219.95.244.227:1521/IBSDEMO
schema: CAS
pas...
Wijayanti Nitya
16:59 Task #814: Company Module
fixing bugs:
- Special char that are allowed for company name are ().'
open/close parenthesis, dot, single quote...
Wijayanti Nitya
16:22 Task #816: Token Module
tested by hafiz
status failed
Token management
1) go to Session Expired to when enter all data that u give
...
Hafizudin MD
14:28 Task #816 (Development / Work In Progress): Token Module
please include DPX File, Batch No. ,Import Key. Hafizudin MD
12:01 Task #814 (Development / Work In Progress): Company Module
Tested by hafiz
status : failed
*Company*
Search
1) Enter Special character () to Company Name. Get this er...
Hafizudin MD

April 04, 2011

09:56 Task #823: Synchronize Token
please use database:
219.95.244.227:1521/IBSDEMO
schema: CAS
pass:password
tq
Wijayanti Nitya
09:55 Task #816 (Internal Testing): Token Module
please use:
219.95.244.227:1521/IBSDEMO
schema: CAS
pass:password
tq
Wijayanti Nitya
09:51 Task #814 (Internal Testing): Company Module
Please use database:
219.95.244.227:1521/IBSDEMO
schema: CAS
pass:password
tq
Wijayanti Nitya

March 29, 2011

11:45 Task #821: Change Authentication Mode
add upass implementation for change authentication mode (return 0) Wijayanti Nitya
11:27 Task #821 (Development / Work In Progress): Change Authentication Mode
Done for Change Authentication mode until:
- shows details
- pending page (maker/checker)
- authorization (still n...
Wijayanti Nitya

March 28, 2011

19:51 Task #823 (Internal Testing): Synchronize Token
Done synchronize token :
- details
- pending
- authorization
Wijayanti Nitya
19:49 Task #824: Dual Control for CAS Administrator
Done Maker Checker for:
- Delete user
- Reset user password
- Enable user
- Disable user
- Assign token
- Unass...
Wijayanti Nitya

March 21, 2011

12:38 Task #824: Dual Control for CAS Administrator
done for Authorization --> Load token Wijayanti Nitya

March 18, 2011

10:13 Task #824 (Development / Work In Progress): Dual Control for CAS Administrator
starting checker / authorization module for load token Wijayanti Nitya
09:51 Task #816 (Work Completed-End life cycle): Token Module
So far, already completed the token module.
But still keep noted if any changes or additional things needed in the ...
Wijayanti Nitya
09:47 Task #814 (Work Completed-End life cycle): Company Module
So far, already completed the company module.
But still keep noted if any changes or additional things needed in th...
Wijayanti Nitya

March 17, 2011

18:50 Task #827 (Closed - End of life cycle): Data Import Module for User Migration
Data Import Module for User Migration Anonymous
18:49 Task #826 (Work Completed-End life cycle): User Status Update Module
Batch Program for User Status Update Module Anonymous
18:48 Task #825 (Closed - End of life cycle): Audit Log - Before & After Update Detail
Audit Log - Before & After Update Detail Anonymous
18:47 Task #824 (Closed - End of life cycle): Dual Control for CAS Administrator
Apply maker/checker flow to CAS Admin User Module Anonymous
18:46 Task #823 (Rejected - End of life cycle): Synchronize Token
User Module - Synchronize Token, as per BRS item 12 Anonymous
18:44 Task #822 (Closed - End of life cycle): Authentication Module Customization
Authentication Module Customization Anonymous
18:44 Task #821 (Rejected - End of life cycle): Change Authentication Mode
User Module - Change Authentication Mode, as per BRS item 15 Anonymous
18:42 Task #820 (Closed - End of life cycle): New Interfaces Development
New Interfaces Development Anonymous
18:41 Task #819 (Closed - End of life cycle): Custody Finalizes Interface
Custody Finalizes Interface Anonymous
18:40 Task #818 (Closed - End of life cycle): SMS Integration
SMS Integration Anonymous
18:39 Task #817 (Work Completed-End life cycle): Add DB Tables
Create & Update DB Schema Anonymous
18:38 Task #816 (Closed - End of life cycle): Token Module
To complete Token Module, as per CAS Admin Module BRS, item 21, 22, 23 & 24 Anonymous
18:35 Task #815 (Closed - End of life cycle): Batch Module
Complete Batch Process, as per CAS Admin Module BRS item 7 & 8 Anonymous
18:33 Task #814 (Closed - End of life cycle): Company Module
To create complete Company Module, as per CAS Admin Module BRS item 3, 4, 5 & 6 Anonymous
 