Activity

From May 04, 2011 to June 02, 2011

May 25, 2011

11:38 Task #825 (User Acceptance Test): Audit Log - Before & After Update Detail
tested by hafiz
status passed
Hafizudin MD

May 23, 2011

09:44 Task #827 (Pending Customer Feedback): Data Import Module for User Migration
Added data import for VASCO, Company and User Cheang Danniell

May 18, 2011

14:51 Task #825: Audit Log - Before & After Update Detail
Wijayanti Nitya wrote:
> 1. fix log status depending on the condition of dual/secondary control whether it is succes...
Wijayanti Nitya
12:27 Task #825 (Internal Testing): Audit Log - Before & After Update Detail
1. fix log status depending on the condition of dual/secondary control whether it is successful/pending for all modul... Wijayanti Nitya

May 09, 2011

04:17 Task #855 (User Acceptance Test): Change Password
tested by hafiz
status Passed
Hafizudin MD
17:14 Task #855 (Internal Testing): Change Password
fixing errors as reported above Wijayanti Nitya

May 04, 2011

16:16 Task #815 (User Acceptance Test): Batch Module
tested by hafiz
status passed
Hafizudin MD
16:10 Task #852 (User Acceptance Test): Admin Navigation Module
tested by hafiz
status passed
Hafizudin MD
15:55 Task #815 (Internal Testing): Batch Module
fixing bugs:
1. restrict validation for date
2. edit error message if submit without clicking checkbox
Wijayanti Nitya
15:47 Task #852 (Internal Testing): Admin Navigation Module
fix bugs:
1. change template (not using the bread-crumb template)
2. add back button at details and edit result page
Wijayanti Nitya
13:36 Task #814 (User Acceptance Test): Company Module
Tested by hafiz
status passed
Hafizudin MD
10:30 Task #814 (Internal Testing): Company Module
fix bugs:
-add back button at create company result page
Wijayanti Nitya

May 03, 2011

00:31 Task #710 (Closed - End of life cycle): Maybank CAS: Requirement Study
Anonymous
 