Activity
From December 21, 2010 to January 19, 2011
January 04, 2011
- 14:56 Task #707 (Work Completed-End life cycle): MPI Phase 1b: Create ESB Request beans, Response beans...
- add mock up for
-check cutting inquiry
-check warehousing
-check reorder
January 03, 2011
- 09:50 Task #707 (Development / Work In Progress): MPI Phase 1b: Create ESB Request beans, Response bean...
- ESB services done(without mock up response)
-check cutting inquiry
-check warehousing
December 31, 2010