Activity

From August 04, 2017 to September 02, 2017

August 16, 2017

15:18 Task #7643 (Pending SIT Deployment): PLN Prepaid - Test Result
Updated document, please download again from Alfresco Anonymous
15:18 Task #7642 (Pending SIT Deployment): PLN Non Taglis - Test Result
Updated document, please download again from Alfresco Anonymous
15:17 Task #7641 (Pending SIT Deployment): PLN Postpaid - Test Result
Updated document, please download again from Alfresco Anonymous

August 14, 2017

13:45 Task #7643 (Pending Review): PLN Prepaid - Test Result
Updated test script, please help to check amy
https://hub.penril.net/share/page/site/maybank-bii-internet-banking/...
Tommy Arryandy
13:44 Task #7642 (Pending Review): PLN Non Taglis - Test Result
Updated test script, please help to check amy
https://hub.penril.net/share/page/site/maybank-bii-internet-banking/...
Tommy Arryandy
13:44 Task #7641 (Pending Review): PLN Postpaid - Test Result
Updated test script, please help to check amy
https://hub.penril.net/share/page/site/maybank-bii-internet-banking/...
Tommy Arryandy

August 07, 2017

17:01 Task #7643 (Internal Testing): PLN Prepaid - Test Result
Updated the document, please download from Alfresco.
Please also check on whether the amount are correctly deducted ...
Anonymous
17:01 Task #7642 (Internal Testing): PLN Non Taglis - Test Result
Updated the document, please download from Alfresco.
Please also check on whether the amount are correctly deducted ...
Anonymous
16:58 Task #7641 (Internal Testing): PLN Postpaid - Test Result
Updated the document, please download from Alfresco.
please also check on whether the amount are correctly deduct...
Anonymous
14:55 Task #7641 (Pending Review): PLN Postpaid - Test Result
Dear Amy need help to review
Tommy Arryandy
14:54 Task #7642: PLN Non Taglis - Test Result
Dear Amy need help to review
Tommy Arryandy
14:50 Task #7643 (Pending Review): PLN Prepaid - Test Result
Dear Amy need help to review Tommy Arryandy

August 04, 2017

15:02 Task #7631 (Closed - End of life cycle): PLN Postpaid - Incorrect Screen at Step 2
Tommy Arryandy
15:02 Task #7631 (Internal Testing): PLN Postpaid - Incorrect Screen at Step 2
Tommy Arryandy
15:01 Task #7628 (Closed - End of life cycle): PLN Prepaid Token Price Sorting
Tommy Arryandy
15:01 Task #7630 (Closed - End of life cycle): PLN Prepaid - Incorrect Exchange Rate
Tommy Arryandy
15:00 Task #7630 (Internal Testing): PLN Prepaid - Incorrect Exchange Rate
Tommy Arryandy
15:00 Task #7636 (Closed - End of life cycle): PLN Non Taglis - Incorrect Exchange Rate
Tommy Arryandy
15:00 Task #7636 (Internal Testing): PLN Non Taglis - Incorrect Exchange Rate
Tommy Arryandy
14:59 Task #7637 (Closed - End of life cycle): PLN Non Taglis - Incorrect Screen at Step 4
Tommy Arryandy
14:59 Task #7635 (Closed - End of life cycle): PLN Postpaid - Incorrect Exchange Rate
Tommy Arryandy
14:59 Task #7635 (Internal Testing): PLN Postpaid - Incorrect Exchange Rate
Tommy Arryandy
14:58 Task #7634 (Closed - End of life cycle): PLN Non Taglis - Incorrect Screen at Step 3
Tommy Arryandy
14:58 Task #7633 (Closed - End of life cycle): PLN Postpaid - Incorrect Screen at Step 4
Tommy Arryandy
14:58 Task #7632 (Closed - End of life cycle): PLN Postpaid - Incorrect Screen at Step 3
Tommy Arryandy
14:57 Task #7639 (Closed - End of life cycle): PLN Non Taglis - Incorrect Screen at Step 2
Tommy Arryandy
 

Also available in: Atom