Activity
From July 18, 2017 to August 16, 2017
August 16, 2017
- 15:15 Task #7724 (Pending SIT Deployment): Release Notes
- Reviewed
- 15:14 Task #7723 (Pending SIT Deployment): Deployment Guidelines
- Reviewed
August 09, 2017
- 07:12 Task #7724 (Pending Review): Release Notes
- Amy,
Please review:
https://hub.penril.net/share/s/5ElEnglWRoubJcLuUNOQ7w
https://hub.penril.net/share/s/haJ6I... - 07:10 Task #7724 (Documentation): Release Notes
- 07:09 Task #7724 (Work Completed-End life cycle): Release Notes
- To compile Release Notes
- 07:08 Task #7723 (Pending Review): Deployment Guidelines
- Amy,
Please review: https://hub.penril.net/share/s/TLbBIAL5SFuyapbXrf1fVQ
Thanks. - 07:07 Task #7723 (Work Completed-End life cycle): Deployment Guidelines
- to prepare Deployment Guidelines
- 18:27 Task #7695 (Work Completed-End life cycle): MSS: Merge current STP Branch with OPG.
- 18:27 Task #7695 (Finished Development): MSS: Merge current STP Branch with OPG.
- The merge has been completed and deployed on 8th August, afternoon time.
August 07, 2017
- 13:18 Task #7695 (Work Completed-End life cycle): MSS: Merge current STP Branch with OPG.
- Need to merge existing MSS with OPG functionality.
- 12:54 Task #7685 (Closed - End of life cycle): OPG - Step 1 - Change Merchant Name to Sub Merchant Name
- Issue closed since it is duplicated with 7687.
- 12:54 Task #7685 (Development / Work In Progress): OPG - Step 1 - Change Merchant Name to Sub Merchant ...
- This issue has been fixed on Friday, 4th August 2017. Also this issue was already reported by Pak Wahyu in Customer S...
August 04, 2017
- 15:58 Task #7685 (Closed - End of life cycle): OPG - Step 1 - Change Merchant Name to Sub Merchant Name
- To do below request from Aditya:...