Activity

From January 07, 2021 to February 05, 2021

January 25, 2021

16:56 Task #10107 (System Integration Test): [P1_Extended] : Mobile IOS - Update E-statement
Send SIT for testing
Plan Date : 26/1/21 - 29/1/21
Nurul Athira Abdul Rahim
10:35 Task #10107 (Internal Testing): [P1_Extended] : Mobile IOS - Update E-statement
No issue on IOS.
Only that Adit calling "file type" and filtered TXT file and only allow and display PDF file.
Th...
Nurul Athira Abdul Rahim

January 21, 2021

15:32 Task #10108 (Documentation): [P1_Extended] : Mobile ANDROID - Update E-statement
Tested and passed for scroll bar
Pending test script and sending for SIT for testing
Nurul Athira Abdul Rahim
15:22 Task #10107 (Development / Work In Progress): [P1_Extended] : Mobile IOS - Update E-statement
Hi Adit,
I'd add some more statement, so the total statement on web now 21 but on iOs only display 14 statement.
...
Nurul Athira Abdul Rahim
13:08 Task #11503 (Work Completed-End life cycle): ePFG User Guide
Create ePFG user Guide Nurul Athira Abdul Rahim

January 18, 2021

13:15 Documentation #11498 (Closed - End of life cycle): [RFP_1.5.1] - BRFD : Corporate Credit Card
To prepare BRFD for below requirement:
> System should be able to integrate with Bank’s Credit Card gateway which ...
Norhaidah Md Dasuki
13:13 Task #11497 (Development / Work In Progress): [Phase_2] : RFP 1.5.1 - Corporate Credit Card
Requirement:-
System should be able to integrate with Bank’s Credit Card gateway which allows customer to check bala...
Norhaidah Md Dasuki
09:45 Task #10362 (System Integration Test): [P1_Extended] : IBAM - Email Notification for checker
target date for testing
SIT
18/1/21 - 21/1/21
UAT
25/1/21 - 28/1/21
Nurul Athira Abdul Rahim

January 17, 2021

01:43 Documentation #11494 (Work Completed-End life cycle): [RFP_1.3.1.3] - BRFD : Multiple Batch Window
To prepare BRFD for sign-off as below requirement.... Norhaidah Md Dasuki
01:40 Task #11493 (Development / Work In Progress): [P1_Extended] : RFP 1.3.1.3 - Multiple Batch Window
Bulk payment execution to be automated and will executes thru daily multiple batch execution as per e-PCMCG rules. Norhaidah Md Dasuki
23:48 Task #11491: [P1_Extended] : RFP 1.1.6 - GST Invoice Statement
> Requirement compilation for BRFD Sign-off
> JPD to provide on the current GST Statement sample. To call meeting fo...
Norhaidah Md Dasuki
23:47 Task #11491 (Pending Customer Feedback): [P1_Extended] : RFP 1.1.6 - GST Invoice Statement
To allow User to download GST Invoice statement thru new CIB, which provided by 3rd party service provider with real ... Norhaidah Md Dasuki

January 14, 2021

18:55 Task #10425: [P1_Extended] ANDROID - CDB_Push Notification for authorization
Hi Darren,
Please take notes. This enhancement need to be completed by 15/1/2021. Kindly update the progress. Tq
Norhaidah Md Dasuki
18:54 Task #10424: [P1_Extended] IOS - CDB_Push Notification for authorization
Hi Adit,
Please take notes. This enhancement need to be completed by 15/1/2021. Kindly update the progress. Tq
Norhaidah Md Dasuki

January 08, 2021

03:08 Task #10362 (Internal Testing): [P1_Extended] : IBAM - Email Notification for checker
Nurul Athira Abdul Rahim
 