Activity

From June 07, 2014 to July 06, 2014

July 03, 2014

14:28 Task #4453: R1: Update user profile
for 1. BBO - created from RCMS and update from RCMS
2. BBO - created from RCAS and update from RCMS
CFO - created f...
Anonymous
14:26 Task #4453: R1: Update user profile
Kah Yan, need your help to test the Webservice after completed other development work. TQ Anonymous
13:26 Task #4453 (Internal Testing): R1: Update user profile
Ong Wei Kuan
13:25 Task #4453 (Finished Development): R1: Update user profile
Ong Wei Kuan
11:56 Task #4438: R1: Allow multiple approve for all Authorization screens - Admin Authorization, Token...
Hi Ayu,
1. after reviewed for this 4438, needed to test and create test script for Admin Authorization and Customer ...
Anonymous

July 01, 2014

13:49 Task #4456: R1: 6 Linking User ID status
Hi Ayu, please assist to test and prepare the test script. please refer to the FSD. Anonymous
12:35 Task #4456 (Internal Testing): R1: 6 Linking User ID status
Hi LeeLee,
issue fixed. Kindly retest. TQ.
Ong Wei Kuan
12:34 Task #4456 (Finished Development): R1: 6 Linking User ID status
Ong Wei Kuan
12:26 Task #4456 (Development / Work In Progress): R1: 6 Linking User ID status
please assist to complete this item: 2. if the user become Virtual--> only assigned token, revoke token, syn token st... Anonymous

June 30, 2014

16:02 Task #4447: R1: CFO - User address: Pin Mailer and Pin Letter, no blank in between if has shorten...
please assist to test on the task. Anonymous
14:24 Task #4453 (Development / Work In Progress): R1: Update user profile
Left SDS to update Ong Wei Kuan
11:20 Bug #4460: refer to task 4443 and 4444: Assigned Date From and Assigned Date To
it allow to search for the same date from and same date to with correct value. Anonymous
11:19 Bug #4460 (Work Completed-End life cycle): refer to task 4443 and 4444: Assigned Date From and As...
tested ok. Anonymous
10:26 Bug #4482 (Work Completed-End life cycle): refer to 4442: Token Cover letter - Remove- correspond...
Retested Fine. Hosseiny Elham

June 27, 2014

16:50 Bug #4482 (Internal Testing): refer to 4442: Token Cover letter - Remove- corresponding address i...
Fixed and deployed. Please retest on Monday.
Thank you.
Yap Kah Yan
11:29 Task #4438: R1: Allow multiple approve for all Authorization screens - Admin Authorization, Token...
Pls refer to Alfresco to get the lastest FSD version. Anonymous
11:14 Bug #4482: refer to 4442: Token Cover letter - Remove- corresponding address issue
change the title description Anonymous

June 25, 2014

17:51 Bug #4482 (Work Completed-End life cycle): refer to 4442: Token Cover letter - Remove- correspond...
Kindly assist to solve it .
Pin Maliler - Development Environment
# Click on Token Cover Letter
# Click on Sea...
Hosseiny Elham
17:10 Task #4473: R1: Exception Report
refer to FSD RCAS FSD reLocII ver 1.0 19 June in Alfreso. Anonymous
15:59 Task #4446 (Pending SIT Deployment): R1 - Create and Edit Company
tested ok. Anonymous
15:25 Bug #4477 (Work Completed-End life cycle): 4446 - edit company - last page
tested. ok Anonymous
15:23 Bug #4476 (Work Completed-End life cycle): 4446 - edit company - cif
tested. ok Anonymous

June 23, 2014

15:05 Bug #4460 (Internal Testing): refer to task 4443 and 4444: Assigned Date From and Assigned Date To
Yap Kah Yan
15:05 Task #4438 (Internal Testing): R1: Allow multiple approve for all Authorization screens - Admin A...
Yap Kah Yan
15:05 Task #4438 (Finished Development): R1: Allow multiple approve for all Authorization screens - Adm...
Yap Kah Yan
14:28 Task #4456 (Internal Testing): R1: 6 Linking User ID status
Ong Wei Kuan
14:28 Task #4456 (Finished Development): R1: 6 Linking User ID status
Ong Wei Kuan
14:27 Bug #4476 (Internal Testing): 4446 - edit company - cif
Ong Wei Kuan
14:27 Bug #4477 (Internal Testing): 4446 - edit company - last page
Ong Wei Kuan
14:26 Bug #4476 (Finished Development): 4446 - edit company - cif
Ong Wei Kuan
14:26 Bug #4477 (Finished Development): 4446 - edit company - last page
Ong Wei Kuan

June 19, 2014

17:19 Task #4446: R1 - Create and Edit Company
Bug 4476: this issue is not cause by Wei Kuan after amended the CIF field. however l need this to be fix before l can... Anonymous
17:18 Bug #4477: 4446 - edit company - last page
this issue is not cause by Wei Kuan after amended the CIF field. Anonymous
17:14 Task #4446: R1 - Create and Edit Company
Completed but waiting 2 bugs to be fixed.
Bug 4476
Bug 4477
Anonymous
17:13 Bug #4477 (Work Completed-End life cycle): 4446 - edit company - last page
click Company, Search company, select provider = Malaysia, click Search. Click until the last page, it through error ... Anonymous
17:08 Bug #4476 (Work Completed-End life cycle): 4446 - edit company - cif
after edit the CIF, and click confirm, it through not allow to edit. Anonymous
11:22 Task #4447 (Internal Testing): R1: CFO - User address: Pin Mailer and Pin Letter, no blank in bet...
Ong Wei Kuan
11:22 Task #4447 (Finished Development): R1: CFO - User address: Pin Mailer and Pin Letter, no blank in...
Ong Wei Kuan

June 18, 2014

17:19 Task #4473 (Closed - End of life cycle): R1: Exception Report
refer to FSD. Anonymous
16:59 Task #4453: R1: Update user profile
this fsd is not a final copy, but for update user profile is ok. Anonymous

June 17, 2014

17:32 Task #4446 (Internal Testing): R1 - Create and Edit Company
Ong Wei Kuan
17:29 Task #4446 (Finished Development): R1 - Create and Edit Company
Ong Wei Kuan

June 16, 2014

15:36 Bug #4463 (Work Completed-End life cycle): Token Managment - Token Listing
fixed and tested fine. Hosseiny Elham
14:48 Bug #4463 (Closed - End of life cycle): Token Managment - Token Listing
kindly assist to fix it thanks.
User ID : casadmin
Password: Maybank124
Development environment.
# Click o...
Hosseiny Elham

June 13, 2014

14:58 Bug #4460 (Closed - End of life cycle): refer to task 4443 and 4444: Assigned Date From and Assig...
the system is allows to search for the same date instead of throw error msg.
eg:
Assigned Date From: 03/06/2014
As...
Anonymous

June 12, 2014

15:05 Task #4456 (Closed - End of life cycle): R1: 6 Linking User ID status
"1. to add on new field: ""Link Indicator"" for user id- A (Active), V (Virtual), - (no link)
2. if the user become ...
Anonymous
15:02 Task #4454 (Closed - End of life cycle): R1: To store Factory ID in RCAS
"1. to create another Application Super user id (factory id) and this ids will have same behaviour like 'Casadmin' (n... Anonymous
15:00 Task #4453 (Closed - End of life cycle): R1: Update user profile
"Update user profile:
Current: if CFO/BBO user status is ""Locked"" or ""Inactive"", or ""Disable"" it not allow to...
Anonymous

June 11, 2014

11:20 Task #4438: R1: Allow multiple approve for all Authorization screens - Admin Authorization, Token...
Hi all
this is add on additional function, please do not remove the current function and progress. They wanted to a...
Anonymous

June 07, 2014

12:29 Task #4447 (Closed - End of life cycle): R1: CFO - User address: Pin Mailer and Pin Letter, no bl...
refer to FSD. Anonymous
11:53 Task #4438: R1: Allow multiple approve for all Authorization screens - Admin Authorization, Token...
pls refer to FSD. Anonymous
11:51 Task #4446: R1 - Create and Edit Company
pls refer to FSD as attached. Anonymous
11:50 Task #4446 (Closed - End of life cycle): R1 - Create and Edit Company
Anonymous
11:37 Task #4425 (Pending SIT Deployment): R1 - Token Reservation for Company
Anonymous
11:36 Task #4425: R1 - Token Reservation for Company
added on Checker progress test script.
Elham, please use Maker ID and checker id to perform the test then we will no...
Anonymous
10:12 Task #4426 (Pending SIT Deployment): R1 - Maintenance – Security Policy
change status to Pending SIT deployment since it require to deploy during SIT phase. Anonymous
 

Also available in: Atom