July 23, 2010
- 16:15 Document: Baseline Project Plan
- The project plan based line
- 13:49 Document: Project Kick Off Slide
- This documents contains project milestone and schedule agreed by both parties
- 13:47 Document: Status Report - 16/07/2010
- July 16 2010 status report update
- 13:44 Task #306 (Work Completed-End life cycle): Taylor Portal Revamp Deployment Preparation & Support
- Prepare deployment plan and provide deployment support
- 13:41 Task #305 (Work Completed-End life cycle): Monitor and support UAT for Taylor Portal Revamp
- Monitor and support UAT process until UAT signed off
- 13:40 Task #304 (Work Completed-End life cycle): Develop the Student Portal
- Implement the Student Portal based on the signed off design
- 13:39 Task #303 (Work Completed-End life cycle): Develop the Parent Portal
- Implement the Parent Portal based on the signed off design
- 11:43 Task #302 (Work Completed-End life cycle): Monitor and ensure Design delivery
- Monitor and ensure the design is delivery by MC on time and also conduct review with stakeholder.
This task can be c... - 11:40 Task #165: Create branch project in Mercurial
- Please get the latest code from Andy to have a good stable version.
July 12, 2010
- 20:05 Task #166 (Closed - End of life cycle): Create Project Schedule
- Created the based line project schedule with the WBS.