- 17:26 Task #565: Setup BV8.1AB on own laptop
- Done all the step from:
1) 2.0 Modifying BV_EDITORIAL table
2) 4.0 Extending Content Types
3) 5.0 Managing New C... - 17:20 Task #565: Setup BV8.1AB on own laptop
- Already done the setup. But not yet tested. I need ID on the taylor student, parent, staff to test it is successful. ...
October 19, 2010
- 11:51 Task #565 (Development / Work In Progress): Setup BV8.1AB on own laptop
- Done Installing BV8.1 Broadvision
October 18, 2010
- 17:11 Task #566 (Closed - End of life cycle): Setup Taylor Content to BV
- Get the Taylor content structure from Amy and setup the Taylor development environement
- 17:08 Task #565 (Closed - End of life cycle): Setup BV8.1AB on own laptop
- 17:01 Task #302 (Work Completed-End life cycle): Monitor and ensure Design delivery
- MC delivered the final HTML template on October 12, 2010
September 30, 2010
- 14:48 Task #303: Develop the Parent Portal
- Update this task.
- 14:47 Task #304: Develop the Student Portal
- Update this task
- 14:47 Task #302: Monitor and ensure Design delivery
- Please do status update and also update the due date. Can upload the final design here if possible