20:25 Change #5557: [TPMS_Review] Issue #39 - 6.1 All Programmes Types Except JPPPA
Hi Leo,
Kindly assist to test.
Siti Norahayu Mohd Desa
20:07 Bug #5558 (Work Completed-End life cycle): [TPMS_Review] Issue #54 - 6.1 All Programmes Types Exc...
21/10/15 [Ayu]
Tested & Passed. Issue closed.
Siti Norahayu Mohd Desa
18:07 Change #5557 (Development / Work In Progress): [TPMS_Review] Issue #39 - 6.1 All Programmes Types...
Please retest after deploy and refer below information.
1. Feedback Setup >> Immediate Feedback
-Field Auto-...
Ngoh Chee Ping
16:44 Bug #5558 (Internal Testing): [TPMS_Review] Issue #54 - 6.1 All Programmes Types Except JPPPA
Fixed. Please retest after deploy.
TQ
Ngoh Chee Ping
11:59 Bug #5500 (Development / Work In Progress): Post Event >> JPPPA Reports
Norhaidah Md Dasuki

October 20, 2015

12:34 Bug #5561 (Work Completed-End life cycle): [TPMS_Review] Issue #49 - 6.3 Budget Utilization
20/10/15 [Ayu] - Tested & Passed. Siti Norahayu Mohd Desa

October 19, 2015

20:30 Bug #5561 (Internal Testing): [TPMS_Review] Issue #49 - 6.3 Budget Utilization
Done, Please retest after deploy Ngoh Chee Ping

October 13, 2015

18:17 Bug #5561 (Work Completed-End life cycle): [TPMS_Review] Issue #49 - 6.3 Budget Utilization
# To add Event Name
# To add field budget utilized depending on submitted Borang P,
# To add column for HQ, RO, TC...
Siti Norahayu Mohd Desa
18:13 Bug #5559 (Work Completed-End life cycle): [TPMS_Review] Issue #47 - 6.2 JPPPA Specific
+URS-MRP008-MRP012+
*1. View Screen - Add 'Sales Generated' column (Automatically calculated by TPMS)*
*2. List...
Siti Norahayu Mohd Desa
17:56 Bug #5558 (Work Completed-End life cycle): [TPMS_Review] Issue #54 - 6.1 All Programmes Types Exc...
Total Participating company should display as total of company, not total of sent reminders. Siti Norahayu Mohd Desa
17:55 Change #5557 (Work Completed-End life cycle): [TPMS_Review] Issue #39 - 6.1 All Programmes Types ...
*1. Feedback Setup >> Immediate Feedback*
* Field Auto-Sent Reminder - to add Tool-tips and Description
*2. Fee...
Siti Norahayu Mohd Desa
11:30 Bug #5500: Post Event >> JPPPA Reports
1. Same Issues still exists. Please Refer to all the attachment.
2. for Outcome/Impact by Programme Type (Summary Va...
Lim Leonard

October 09, 2015

10:44 Bug #5500: Post Event >> JPPPA Reports
fixed, please test after deployed.... Tan Jeng Wei

October 08, 2015

17:51 Bug #5500: Post Event >> JPPPA Reports
8/10/15
there is some issue still havent fixed.
1. Padding between line and text.
2. borders problems.
3. mis...
Lim Leonard
16:49 Bug #5500: Post Event >> JPPPA Reports
fixed....
Tan Jeng Wei

October 05, 2015

12:09 Bug #5500: Post Event >> JPPPA Reports
Hi Jeng Wei,
Please assist in look and feel modification,
you can refer to the previous print screen and list
...
Lim Leonard

October 02, 2015

18:01 Bug #5500: Post Event >> JPPPA Reports
Hi Leonard,
I've updated the sql queries for the 3 reports(no data) and tested fine in db. Kindly retest.
And als...
Ong Wei Kuan
15:29 Bug #5500: Post Event >> JPPPA Reports
Hi Leonard,
Kindly assist to revert the result for below query. Thanks ya.
select month(a.em_start_date) as mo...
Ong Wei Kuan
14:59 Bug #5500: Post Event >> JPPPA Reports
Hi Wei Kuan,
Please check your email,
Thanks
Lim Leonard
14:26 Bug #5500: Post Event >> JPPPA Reports
Yes. Ong Wei Kuan
14:25 Bug #5500: Post Event >> JPPPA Reports
hi Wei Kuan,
the data, do you mean the result from the query?
thanks
Lim Leonard
14:11 Bug #5500: Post Event >> JPPPA Reports
Hi Leonard,
1. For the report desgin, please get Jeng Wei to assist on this. TQ.
2. For the data checking, can yo...
Ong Wei Kuan
12:51 Bug #5500: Post Event >> JPPPA Reports
Hi WeiKuan,
-for the reports with no data, i have already checked the database. there is data in the database, but...
Lim Leonard

October 01, 2015

18:14 Bug #5500: Post Event >> JPPPA Reports
HI Leonard,
1. fast fact -No. of Programme by month -> no data
--> I tested at my local, there are data in the re...
Ong Wei Kuan
11:13 Bug #5500: Post Event >> JPPPA Reports
Hi WeiKuan,
there are some bugs that need to be solved:
fast fact -No. of Programme by month -> no data
report...
Lim Leonard

September 28, 2015

11:27 Bug #5489 (Work Completed-End life cycle): Test Ref# 8.1: Post Event >> Event Listing
28/9/2015 [Ayu]
Tested. Issue closed.
Siti Norahayu Mohd Desa
08:39 Bug #5500 (Internal Testing): Post Event >> JPPPA Reports
Hi Leonard,
I've pushed the fixes, you may retest after redeployment later. TQ.
Ong Wei Kuan
 