Activity

From February 07, 2016 to March 07, 2016

March 07, 2016

16:05 Task #6039 (Work Completed-End life cycle): Event Report > IBM > Sales By Malaysian Exporters
Hi Jeng Wei,
The report is not displayed, for PDF and Excel
Please fix this report
Lim Leonard

March 03, 2016

16:06 Module 3: Promotion Bug #6030 (Work Completed-End life cycle): [Prod_Issue] - Promotion - Malaysian Company & Foreign...
*Malaysia Company:-*
1. Sort Company Name alphabetically
2. Product & Service column change to Product / Service S...
Siti Norahayu Mohd Desa

February 15, 2016

09:31 Module 4: Publication Bug #5857 (Work Completed-End life cycle): Publication>Email Marketing
Issue 2:((DONE. Tested and Passed) Norhaidah Md Dasuki

February 12, 2016

11:21 Module 4: Publication Bug #5857 (Internal Testing): Publication>Email Marketing
Hi haidah
issues: coding was remove.
Tan Jeng Wei
 

Also available in: Atom