Task #10365
Migration Plan Document
Status: | Development / Work In Progress | Start date: | October 17, 2019 | ||
---|---|---|---|---|---|
Priority: | Normal | Due date: | October 17, 2019 | ||
Assignee: | Chun Feng Lim | % Done: | 90% | ||
Category: | - | Spent time: | - | ||
Target version: | - |
Description
Dear CF,
As spoken, need your kind assistance to prepare migration plan document for Tech Refresh.
I proposed to have 2 migration night (first night is for migration drill. Why? Because as I understand from you, current Tech Refresh Host and DB are still connecting to UAT staging. There is no connection testing done to PROD HOST and PROD DB yet.
Sample migration document as attached (taken from CUA).
Thank you.
History
#1 Updated by Chun Feng Lim almost 5 years ago
- File Agro Tech Refresh.doc added
- % Done changed from 0 to 90
Document Update, there are few items left. Fell free to review if I left out anything.