Task #1039

eCustody User Guide

Added by Vincent Devethas about 13 years ago. Updated almost 13 years ago.

Status:Work Completed-End life cycleStart date:July 25, 2011
Priority:NormalDue date:August 05, 2011
Assignee:Vincent Devethas% Done:

100%

Category:-Estimated time:40.00 hours
Target version:-Spent time:41.00 hours

Description

Prepate user guide for eCustody System (Custody main). Document should contain:
(1) step by step instruction.
(2) screen shot of each step with some description.
(3) Form input values should place in a table with data type and example.
(4) Must follow the flow of process. Eg. initiate trade > verifiy trade > authorize trade > send trade

History

#1 Updated by Almasi Moein about 13 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • % Done changed from 0 to 90

Prepate user guide for eCustody System (Custody main). Document should contain:
(1) step by step instruction. - DONE
(2) screen shot of each step with some description. - DONE
(3) Form input values should place in a table with data type and example. - DONE
(4) Must follow the flow of process. Eg. initiate trade > verifiy trade > authorize trade > send trade. - DONE
-------------------------------------------------------------------------------------------------------
Step by step guideline of the eCustody main system, completely demonstrate step by step with screenshots and explanation

10% remaining is that some of the modules doesn't have data to put the screenshots therefore will be completed upon adding those screenshots.

Document properties: 155 Page so far and approx of 10,000 words

#2 Updated by Almasi Moein about 13 years ago

  • Due date changed from July 29, 2011 to August 05, 2011
  • Assignee changed from Almasi Moein to Vincent Devethas
  • % Done changed from 90 to 100

10% remaining is that some of the modules doesn't have data to put the screenshots therefore will be completed upon adding those screenshots. Done

eCustody user manual has been assigned to Vincent in order to double check and comment on the document, and if requires any correction I will do it before handover to client by today.

#3 Updated by Vincent Devethas almost 13 years ago

  • Status changed from Development / Work In Progress to Work Completed-End life cycle

user manual has been compiled and given to user

Also available in: Atom PDF