Change #10513
Bug #10089: Issue to be FIXED / RE-FIXED
Demo Mobile (IOS and Android)
Status: | Work Completed-End life cycle | Start date: | December 17, 2019 | |
---|---|---|---|---|
Priority: | Normal | Due date: | December 18, 2019 | |
Assignee: | - | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Create demo for BSNeBiz Mobile for Android and IOS.
History
#2 Updated by Anonymous almost 5 years ago
Tested and passed.
#3 Updated by Anonymous almost 5 years ago
- Status changed from Work Completed-End life cycle to System Integration Test
- % Done changed from 0 to 100
#4 Updated by Anonymous almost 5 years ago
- Parent task set to #10089
#5 Updated by Norhaidah Md Dasuki almost 5 years ago
- Due date set to December 18, 2019
- Status changed from System Integration Test to Pending UAT Deployment
- Assignee changed from Anonymous to Aditya Prathama
- Start date changed from December 06, 2019 to December 17, 2019
- % Done changed from 100 to 80
Rahmat Mohd Mohd Aris (Channels & Non-Core Application, JTM, BSN) Fri, Dec 6, 9:38 AM (11 days ago) to me, JTM,, Lee, JTM,, Nurul, Penril Waalaikumussalam Puan, Testing for SIT already completed.
Aditya,
Please assist to ensure the UAT environment for this enhancement ready for User testing.
#6 Updated by Aditya Prathama over 4 years ago
- Assignee changed from Aditya Prathama to Nur Syamili Abdul Majid
re assign to mili
@mili please make sure uat build ready for this
#7 Updated by Nur Syamili Abdul Majid over 4 years ago
- Status changed from Pending UAT Deployment to Internal Testing
- Assignee changed from Nur Syamili Abdul Majid to Anonymous
Pls test thank you
#8 Updated by Anonymous over 4 years ago
- Status changed from Internal Testing to User Acceptance Test
Tested and passed.
Waiting for UAT testong.
#9 Updated by Anonymous over 4 years ago
- Status changed from User Acceptance Test to Work Completed-End life cycle
- % Done changed from 80 to 100