Task #10600
IBSCR19015: EPF Contribution information to be reflected at account statement (SCP#5163)
Status: | Dropped-End of life cycle | Start date: | January 22, 2020 | |
---|---|---|---|---|
Priority: | Normal | Due date: | January 27, 2020 | |
Assignee: | Yap Kah Yan | % Done: | 0% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Refer to attached document:
To change as per below:
To send the following EPF Contribution information to Core (Transaction Description).
i. Payment Code
ii. Contribution Month
iii. Employer EPF No
iv. Employer Name
Sample and expected result to be reflected in the statement.
IB:EPF Pymt Code: S. Ctb Mo: 102019. EPF No. 06171629. Employer Name:lee yung sang
IB:EPF<space>Pymt Code:<1 character><space>Ctb Mo:<mmyyyy><space>EPF No:<15characters><space>Emp Name:<15characters>
Breakdown:
IB:EPF 6
<space> 1
Pymt Code: 10
<pymtcode> 1
<space> 1
Ctb Mo: 7
<mmyyyy> 4
<space> 1
EPF No: 7
<epfNoValue> 15
<space> 1
Emp Name: 9
<name> 15
History
#1 Updated by Yap Kah Yan over 4 years ago
IB:EPF<space>Pymt Code:<1 character><space>Ctb Mo:<mmyyyy><space>EPF No:<15characters><space>Emp Name:<15characters>
#2 Updated by Yap Kah Yan over 4 years ago
Yap Kah Yan wrote:
Refer to attached document:
To change as per below:
To send the following EPF Contribution information to Core (Transaction Description).
i. Payment Code
ii. Contribution Month
iii. Employer EPF No
iv. Employer NameSample and expected result to be reflected in the statement.
IB:EPF Pymt Code: S. Ctb Mo: 102019. EPF No. 06171629. Employer Name:lee yung sang
IB:EPF<space>Pymt Code:<1 character><space>Ctb Mo:<mmyyyy><space>EPF No:<15characters><space>Emp Name:<15characters>Breakdown:
IB:EPF 6
<space> 1
Pymt Code: 10
<pymtcode> 1
<space> 1
Ctb Mo: 7
<mmyyyy> 4
<space> 1
EPF No: 7
<epfNoValue> 15
<space> 1
Emp Name: 9
<name> 15
#3 Updated by Lizahwati Basirun about 4 years ago
- Assignee changed from Amran Siti Nadhirah to Yap Kah Yan
Dear Kahyan,
Please update on this development.
Thank you.
#4 Updated by Yap Kah Yan over 3 years ago
- Status changed from New - Begin Life Cycle to Pending Customer Feedback
pending feedback on the timeline for this project
#5 Updated by Yap Kah Yan almost 3 years ago
- Status changed from Pending Customer Feedback to Dropped-End of life cycle
Issue closed / dropped due to no update from KFH on the quotation