Support #11291
[SCP ID :##5586##] : Missing line in eStatement
Status: | Closed - End of life cycle | Start date: | October 07, 2020 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Nurul Athira Abdul Rahim | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Hi,
Kindly attend below request:-
Missing line in eStatement. Relate to SCPID 5498
History
#1 Updated by Nurul Athira Abdul Rahim almost 4 years ago
- Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin
#2 Updated by Najmi Pasarudin almost 4 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
#3 Updated by Najmi Pasarudin almost 4 years ago
- % Done changed from 0 to 90
#4 Updated by Najmi Pasarudin almost 4 years ago
- File Corporate_Statement_DAILY_07-OCT-20.txt added
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim
Issue:
Some eStatement missing last record
Finding:
If eStatement content is divided by a blank line, cronjob will skip the last record because previously blank line is considered no more data.
Solution:
Fix blank line checking.
- Attached is sample of ICBS eStatement file. Edit BSN account for testing.
- Copy the file to SIT Batch server at path /batch/BSN/BatchFilesSIT/eStatement/RawFile.
- After 1 minute, the file will be processed.
- Access IBAM>CBE>eStatement.
- Search for the BSN account.
- From the list, download the new eStatement text and pdf.
- Check the content.
- Expected result, the content in ICBS file, downloaded text and pdf is matching.
#5 Updated by Nurul Athira Abdul Rahim almost 4 years ago
- File 0099929100000545_WDH_20201007 (1).txt added
- Status changed from Internal Testing to System Integration Test
Tested and passed.
#6 Updated by Erni Suhaireen Zulkifli almost 4 years ago
- Status changed from System Integration Test to User Acceptance Test
Hand over to UAT Test
#7 Updated by Nurul Athira Abdul Rahim almost 4 years ago
- Assignee changed from Nurul Athira Abdul Rahim to Nurul Hasnieza Bt Mohd Zamri
Tested and passed on UAT on 9/10/20.
Kindly deploy to pre prod env.
#8 Updated by Nurul Athira Abdul Rahim almost 4 years ago
- Status changed from User Acceptance Test to Pending Prod Deployment
#9 Updated by Erni Suhaireen Zulkifli almost 4 years ago
- File support 11291 SCPID5586.png added
- Assignee changed from Nurul Hasnieza Bt Mohd Zamri to Nurul Athira Abdul Rahim
- % Done changed from 90 to 100
Tested and passed at Preprod
Refer attachment for result details.
Hi Athira,
Please change status for this issue to "Pending Deployment" at Issue Log
#10 Updated by Najmi Pasarudin almost 4 years ago
- Status changed from Pending Prod Deployment to Pending Review
Production deployed on 9/10/2020
#11 Updated by Nurul Athira Abdul Rahim almost 4 years ago
- Status changed from Pending Review to Closed - End of life cycle
Migration ID0019