Status: | Work Completed-End life cycle | Start date: | February 05, 2021 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Siti Balqis Othman | % Done: | 100% | |
Category: | BIB | Spent time: | - | |
Target version: | - |
Description
Hi,
Kindly attend below request:-
EPF registration status for penril not successful update due to contribution month during customer upload and contribution month in the TR file not matched.
Customer file 012021
TR file 022021
As confirm by user, EPF advise to remove contribution month checking for the status update process.
History
#1 Updated by Siti Balqis Othman over 3 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
#2 Updated by Siti Balqis Othman over 3 years ago
- Status changed from Development / Work In Progress to Pending SIT Deployment
- % Done changed from 0 to 100
#3 Updated by Siti Balqis Othman almost 3 years ago
- Status changed from Pending SIT Deployment to Finished Development
#4 Updated by Siti Balqis Othman almost 3 years ago
- Status changed from Finished Development to Code Review
#5 Updated by Siti Balqis Othman almost 3 years ago
- Status changed from Code Review to Development / Work In Progress
#6 Updated by Siti Balqis Othman almost 3 years ago
- Status changed from Development / Work In Progress to Work Completed-End life cycle
Migrated to production
Migration ID 170