Support #11538

[SCP ID :##5754##] : Request to include pending submission status in expiry checking

Added by Zahir Abd Latif over 3 years ago. Updated over 3 years ago.

Status:Work Completed-End life cycleStart date:February 11, 2021
Priority:NormalDue date:February 17, 2021
Assignee:Zahir Abd Latif% Done:

100%

Category:-Spent time:-
Target version:-

Description

Hi,
Kindly attend below request:-

Request to include pending submission status in expiry checking so that the old pending submission status will be no longer display at user list.

11538 - Add the Expiry Date checking for Pending Submission.docx (4.03 MB) Nurul Athira Abdul Rahim, February 18, 2021 20:18

History

#1 Updated by Nurul Athira Abdul Rahim over 3 years ago

  • Due date set to February 17, 2021
  • Assignee changed from Nurul Athira Abdul Rahim to Nurul Hasnieza Bt Mohd Zamri

#2 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress

#3 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago

  • Status changed from Development / Work In Progress to Finished Development
  • % Done changed from 0 to 80

#4 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago

  • Status changed from Finished Development to Internal Testing
  • Assignee changed from Nurul Hasnieza Bt Mohd Zamri to Nurul Athira Abdul Rahim

Hi Athira,
done deployment at SIT environment. Kindly retest.

Finding: There is no checking expired date for Pending Submission.
Solution: Add the Expiry Date checking for Pending Submission.

For the expiry day duration is set to 37 days. The batch server running is set to 12 am.
For testing can manually run the updateApplicationFormStatus.sh in batch server.
The updated date has been update in database for:
-today
-yesterday
-before 40 days

#5 Updated by Nurul Athira Abdul Rahim over 3 years ago

Tested and passed

#6 Updated by Nurul Athira Abdul Rahim over 3 years ago

  • Status changed from System Integration Test to Pending UAT Deployment
  • Assignee changed from Nurul Athira Abdul Rahim to Nurul Hasnieza Bt Mohd Zamri

Tested and passed by azyan on 23/2/21

Please prepare for uat deployment.

#7 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago

  • Status changed from Pending UAT Deployment to Code Review

#8 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago

  • Status changed from Code Review to Finished Development

#9 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago

  • Status changed from Finished Development to Internal Testing

#10 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago

  • Status changed from Internal Testing to User Acceptance Test
  • Assignee changed from Nurul Hasnieza Bt Mohd Zamri to Nurul Athira Abdul Rahim

Athira,
done UAT deployment at 24/02/2021.

#11 Updated by Nurul Athira Abdul Rahim over 3 years ago

  • Status changed from User Acceptance Test to Pending Prod Deployment
  • Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin

Tested and passed by Mazni on 25/2/21

Please prepare for preprod deployment

Thanks

#12 Updated by Najmi Pasarudin over 3 years ago

  • Status changed from Pending Prod Deployment to Pending Review
  • Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim

Production deployed on 05/03/2021

#13 Updated by Nurul Athira Abdul Rahim over 3 years ago

  • Status changed from Pending Review to Work Completed-End life cycle
  • Assignee changed from Nurul Athira Abdul Rahim to Zahir Abd Latif
  • % Done changed from 90 to 100

Also available in: Atom PDF