Support #11837
[SCP ID :##5866##] : SPP Other Report
Status: | Work Completed-End life cycle | Start date: | May 25, 2021 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Zahir Abd Latif | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Hi,
Kindly attend below request:-
SPP module for Other report having issue where by the Other report not display in IBAM. The report is exist in batch server
History
#1 Updated by Nurul Athira Abdul Rahim over 3 years ago
- Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin
#2 Updated by Najmi Pasarudin over 3 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
#3 Updated by Najmi Pasarudin over 3 years ago
- % Done changed from 0 to 90
#4 Updated by Najmi Pasarudin over 3 years ago
- Status changed from Development / Work In Progress to Internal Testing
#5 Updated by Najmi Pasarudin over 3 years ago
- Status changed from Internal Testing to System Integration Test
SIT deployed on 02/06/2021
#6 Updated by Najmi Pasarudin over 3 years ago
- Status changed from System Integration Test to Internal Testing
- Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim
Issue:
IBAM SPP Other report > org code not available
Finding:
IBAM SPP Other report > org code is hardcoded. Only one org code is shown.
Solution:
Fix IBAM SPP Other report > org code to generate all organizations org code
- Prepare report 210 in batch server
- Access IBAM > File Processing > SPP report
- Select State and Report Type > Other
- Org code should shows all org code
- Select the org code for step 1 report
- Expected result, other report is listed and can be downloaded
#7 Updated by Nurul Athira Abdul Rahim over 3 years ago
- Status changed from Internal Testing to System Integration Test
Send for sit testing.
#8 Updated by Nurul Athira Abdul Rahim about 3 years ago
- Status changed from System Integration Test to Development / Work In Progress
- Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin
Tested and failed by Azyan 280621. Report is available in Collection Receivable not in SPP report
#9 Updated by Najmi Pasarudin about 3 years ago
- Status changed from Development / Work In Progress to System Integration Test
- Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim
SIT re-deployed on 06/08/2021
#10 Updated by Nurul Athira Abdul Rahim almost 3 years ago
- Status changed from System Integration Test to Pending Review
- % Done changed from 90 to 100
Deployed to prod on 9/9/21
#11 Updated by Nurul Athira Abdul Rahim almost 3 years ago
- Status changed from Pending Review to Work Completed-End life cycle
- Assignee changed from Nurul Athira Abdul Rahim to Zahir Abd Latif