Support #11837

[SCP ID :##5866##] : SPP Other Report

Added by Zahir Abd Latif over 3 years ago. Updated almost 3 years ago.

Status:Work Completed-End life cycleStart date:May 25, 2021
Priority:NormalDue date:
Assignee:Zahir Abd Latif% Done:

100%

Category:-Spent time:-
Target version:-

Description

Hi,
Kindly attend below request:-

SPP module for Other report having issue where by the Other report not display in IBAM. The report is exist in batch server

History

#1 Updated by Nurul Athira Abdul Rahim over 3 years ago

  • Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin

#2 Updated by Najmi Pasarudin over 3 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress

#3 Updated by Najmi Pasarudin over 3 years ago

  • % Done changed from 0 to 90

#4 Updated by Najmi Pasarudin over 3 years ago

  • Status changed from Development / Work In Progress to Internal Testing

#5 Updated by Najmi Pasarudin over 3 years ago

  • Status changed from Internal Testing to System Integration Test

SIT deployed on 02/06/2021

#6 Updated by Najmi Pasarudin over 3 years ago

  • Status changed from System Integration Test to Internal Testing
  • Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim

Issue:
IBAM SPP Other report > org code not available

Finding:
IBAM SPP Other report > org code is hardcoded. Only one org code is shown.

Solution:
Fix IBAM SPP Other report > org code to generate all organizations org code

Test steps:
  1. Prepare report 210 in batch server
  2. Access IBAM > File Processing > SPP report
  3. Select State and Report Type > Other
  4. Org code should shows all org code
  5. Select the org code for step 1 report
  6. Expected result, other report is listed and can be downloaded

#7 Updated by Nurul Athira Abdul Rahim over 3 years ago

  • Status changed from Internal Testing to System Integration Test

Send for sit testing.

#8 Updated by Nurul Athira Abdul Rahim about 3 years ago

  • Status changed from System Integration Test to Development / Work In Progress
  • Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin

Tested and failed by Azyan 280621. Report is available in Collection Receivable not in SPP report

#9 Updated by Najmi Pasarudin about 3 years ago

  • Status changed from Development / Work In Progress to System Integration Test
  • Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim

SIT re-deployed on 06/08/2021

#10 Updated by Nurul Athira Abdul Rahim almost 3 years ago

  • Status changed from System Integration Test to Pending Review
  • % Done changed from 90 to 100

Deployed to prod on 9/9/21

#11 Updated by Nurul Athira Abdul Rahim almost 3 years ago

  • Status changed from Pending Review to Work Completed-End life cycle
  • Assignee changed from Nurul Athira Abdul Rahim to Zahir Abd Latif