Bug #12031

VIT_183 - Participant Liquidity Status

Added by Nurul Akmal about 3 years ago. Updated about 3 years ago.

Status:Work Completed-End life cycleStart date:June 25, 2021
Priority:NormalDue date:
Assignee:Nurul Akmal% Done:

100%

Category:-Spent time:-
Target version:-

Description

Issue 1:
Download not working - Excel and PDF

Issue 2:
Click Threshold, error: Error while performing your request.

History

#1 Avatar?id=1966&size=24 Updated by Ngoh Chee Onn about 3 years ago

  • Status changed from New - Begin Life Cycle to Internal Testing
  • Assignee changed from Ngoh Chee Onn to Nurul Akmal
  • % Done changed from 0 to 90

Hi Akmal,

Fixed done and deployed into Penril server, fixed will deploy to Ptap server in release beta 16 or 15.1.

Thank you

#2 Updated by Nurul Akmal about 3 years ago

  • Status changed from Internal Testing to Work Completed-End life cycle
  • % Done changed from 90 to 100

Tested successfully and closed in VIT log on 25/06/2021.
Thank you

#3 Updated by Nurul Akmal about 3 years ago

  • Status changed from Work Completed-End life cycle to Development / Work In Progress
  • Assignee changed from Nurul Akmal to Ngoh Chee Onn
  • % Done changed from 100 to 90

VIT_201:
Re-open due to user hit error when click on Threshold details.

Expected:
To trim Participant ID and able to view Threshold details & Download threshold.

#4 Avatar?id=1966&size=24 Updated by Ngoh Chee Onn about 3 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Ngoh Chee Onn to Nurul Akmal

Hi Akmal,

Issue fixed and deployed into Penril server, fixed will deploy into ptap server in release beta 22.

Thank you

#5 Updated by Siti Norahayu Mohd Desa about 3 years ago

  • Status changed from Internal Testing to Work Completed-End life cycle
  • % Done changed from 90 to 100

Tested & Passed. Send for User testing

#6 Updated by Siti Norahayu Mohd Desa about 3 years ago

  • Status changed from Work Completed-End life cycle to User Acceptance Test

#7 Updated by Siti Norahayu Mohd Desa about 3 years ago

  • Status changed from User Acceptance Test to Work Completed-End life cycle

Issue have been closed on 25/6/21 by viki

Also available in: Atom PDF