Feature #12061
Task #11680: [Phase_2] : RFP 1.2.2.3- DuitNow - Instant Transfer
Task #11632: [Phase_2] WEB - DuitNow - Instant Transfer
UAT_DuitNow - Update bulk transaction requirement
Status: | Work Completed-End life cycle | Start date: | July 02, 2021 | |
---|---|---|---|---|
Priority: | Normal | Due date: | July 05, 2021 | |
Assignee: | Nurul Athira Abdul Rahim | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Request by Encik Rahmat to follow existing bulk transaction flow
Currently :
- Customer only allow to select today date
Expected :
- Customer allow to select today and future date. (up to 7 days)
- Authorizer allow to authorize the transaction as long not passed the transation date.
Same goes to upload file module.
History
#1 Updated by Nurul Athira Abdul Rahim about 3 years ago
- Parent task set to #11632
#2 Updated by Norhaidah Md Dasuki about 3 years ago
- Tracker changed from Task to Feature
- Subject changed from DuitNow - Update bulk transaction requirement to UAT_DuitNow - Update bulk transaction requirement
#3 Updated by Najmi Pasarudin about 3 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- % Done changed from 0 to 90
#4 Updated by Najmi Pasarudin about 3 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim
SIT deployed on 09/07/2021
#5 Updated by Nurul Athira Abdul Rahim about 3 years ago
- File updated payment date 1.jpg added
- File updated payment date 2.jpg added
- File updated payment date 3.jpg added
- File updated payment date 4.jpg added
- File updated payment date 5.jpg added
- Status changed from Internal Testing to Work Completed-End life cycle
- % Done changed from 90 to 100
Tested and passed