Feature #12067
Task #11680: [Phase_2] : RFP 1.2.2.3- DuitNow - Instant Transfer
Task #11632: [Phase_2] WEB - DuitNow - Instant Transfer
UAT_DuitNow [MOBILE - IOS] - Recipient Reference
Status: | Work Completed-End life cycle | Start date: | July 02, 2021 | |
---|---|---|---|---|
Priority: | Normal | Due date: | July 05, 2021 | |
Assignee: | Nurul Syahirah Md Nawi | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Update from Encik Rahmat
To default the Recipient Reference to DuitNow Transfer.
Customer allow to edit the Recipient Reference.
Max length : 140
Related issues
History
#1 Updated by Nurul Athira Abdul Rahim about 3 years ago
- Due date set to July 05, 2021
#2 Updated by Norhaidah Md Dasuki about 3 years ago
- Tracker changed from Task to Feature
- Subject changed from DuitNow [MOBILE - IOS] - Recipient Reference to UAT_DuitNow [MOBILE - IOS] - Recipient Reference
#3 Updated by Aditya Prathama almost 3 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Aditya Prathama to Nurul Syahirah Md Nawi
- % Done changed from 0 to 100
miss out to update redmine, this already fixed on PROD version 3.2.8 build 213
#4 Updated by Nurul Syahirah Md Nawi almost 3 years ago
- File Updated_Recipient Ref.jpeg added
- Status changed from Internal Testing to User Acceptance Test
Tested & pass
#5 Updated by Nurul Syahirah Md Nawi over 2 years ago
- Status changed from User Acceptance Test to Work Completed-End life cycle