[BIF - 31797] Fee Calculation Detail Report format doesn't matched with SRS
Status: | Work Completed-End life cycle | Start date: | October 30, 2021 | |
---|---|---|---|---|
Priority: | Normal | Due date: | November 05, 2021 | |
Assignee: | Siti Norahayu Mohd Desa | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Please check fee calculation report follow SRS;
the column name that shows BIC, participant name, and account number should be labelled as "Receiver" column since the report should show only the list for a specific participant.
-In the mockup and actual format generated, it is labelled as "Source".
History
#1 Updated by Ngoh Chee Ping almost 3 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Ngoh Chee Ping to Nurul Akmal
- % Done changed from 0 to 100
The new CR will have separate 2 report, 1 for source, and 1 more for receiver. Already finished the CR have source and receiver fee details report. Therefore this issue is not valid anymore.
#2 Updated by Siti Norahayu Mohd Desa almost 3 years ago
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Nurul Akmal to Bramantyo Pujo Wiyono
Pending Bram to deploy the config file.
#3 Updated by Bramantyo Pujo Wiyono almost 3 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Bramantyo Pujo Wiyono to Siti Norahayu Mohd Desa
- % Done changed from 100 to 80
Already deploy and generate report 01112021-02112021
#4 Updated by Siti Norahayu Mohd Desa almost 3 years ago
- Status changed from Internal Testing to User Acceptance Test
Send for user testing
#5 Updated by Siti Norahayu Mohd Desa almost 3 years ago
- File BIF-31797.png added
- Status changed from User Acceptance Test to Development / Work In Progress
- Assignee changed from Siti Norahayu Mohd Desa to Ngoh Chee Ping
-Based on the latest report generated, fee calculationdetail report for direct participant contains data of its indirect in the same report
-Please kindly separate the data for direct and indirect in the different report>> hence when login as direct participant there should be report for its indirect participant
#6 Updated by Ngoh Chee Ping almost 3 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Ngoh Chee Ping to Siti Norahayu Mohd Desa
- % Done changed from 80 to 100
Updated the report format and updated to server.
#7 Updated by Siti Norahayu Mohd Desa almost 3 years ago
- Due date set to November 05, 2021
- Status changed from Internal Testing to Work Completed-End life cycle
Issue have been Closed and will refer to BIF-35580 by Pak Hafiz on 5 Nov 2021