Bug #13017

[Participant & Admin Report] - Request For Payment Request Detail Report

Added by Sarifah Nurhafizah Nasihah Ibnuhajar over 2 years ago. Updated over 2 years ago.

Status:Work Completed-End life cycleStart date:May 19, 2022
Priority:NormalDue date:
Assignee:Sarifah Nurhafizah Nasihah Ibnuhajar% Done:

80%

Category:-Spent time:-
Target version:-

Description

1) Report title not following SRS - Correct title : Request For Payment Request Detail Report

2) Acc Name for Sender and Receiver not display any data.

Bug - RFP Request Detail.png - Issue 3 (86.4 KB) Sarifah Nurhafizah Nasihah Ibnuhajar, May 24, 2022 18:06

Bug - RFP Request Detail SRS 4.png - issue 4 and 5 (47.7 KB) Sarifah Nurhafizah Nasihah Ibnuhajar, May 24, 2022 18:06

Bug - RFP Request Detail SRS.png - RFP ID Column from SRS (66.4 KB) Sarifah Nurhafizah Nasihah Ibnuhajar, May 24, 2022 18:06

Bug - RFP Request Detail SRS 5.png - Possible values of STATUS from SRS (68.2 KB) Sarifah Nurhafizah Nasihah Ibnuhajar, May 24, 2022 18:06

History

#1 Updated by Bramantyo Pujo Wiyono over 2 years ago

  • Status changed from New - Begin Life Cycle to Internal Testing
  • Assignee changed from Bramantyo Pujo Wiyono to Sarifah Nurhafizah Nasihah Ibnuhajar
  • % Done changed from 0 to 80

For the case no 1 already fixed, but for case no 2 is due to the current data doest had those information

BBUKIDJA
PT. BANK KB BUKOPIN, TBK
RequestForPaymentTransactionRequest_19052022_Daily_2.xlsx

#2 Updated by Sarifah Nurhafizah Nasihah Ibnuhajar over 2 years ago

Tested issue 1 & 2 and passed. Thank you

However, noticed more bugs for this report which are :

3) Title column "TRANSACTION ID" not following SRS.

In SRS, the column is : "RFP ID"

4) Column EXPIRED DATE/TIME not showing data for time

5) Column status display data that is not following SRS :-

In SRS the possible values for STATUS are :

  • Received
  • Settled
  • Rejected

#3 Updated by Sarifah Nurhafizah Nasihah Ibnuhajar over 2 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Sarifah Nurhafizah Nasihah Ibnuhajar to Bramantyo Pujo Wiyono

#4 Updated by Bramantyo Pujo Wiyono over 2 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Bramantyo Pujo Wiyono to Sarifah Nurhafizah Nasihah Ibnuhajar

Issue 3 and 5 has been fix and the report already regenerated. Please help retest again.

For issue 4 the data from hub only provided date

#5 Updated by Sarifah Nurhafizah Nasihah Ibnuhajar over 2 years ago

  • Status changed from Internal Testing to Work Completed-End life cycle

Tested and passed. Thank you